Test <strong>Management</strong> Tool (TMT)<br />
<strong>Software</strong> <strong>Project</strong> <strong>Management</strong> <strong>Plan</strong> (<strong>SPMP</strong>)<br />
TMT-<strong>SPMP</strong>-1.2<br />
27-Sep-2010<br />
Description Date Cost<br />
MS Visual Studio 2010, an IDE. 30-Aug-2010 Free<br />
Configuration <strong>Management</strong> Tool (at<br />
http://adam.404.unfuddle.com).<br />
20-Sep-2010 Paid by Adam<br />
5.1.4. <strong>Project</strong> Staff Training <strong>Plan</strong><br />
There is no plan for project staff planning. It is assumed that the team members assigned to the<br />
TMT team have already been well trained in the pre-requisites of the capstone course. Team<br />
members are assigned with responsibilities based on their initial skill levels and re-evaluated<br />
after each development increment as applicable.<br />
5.2. Work <strong>Plan</strong><br />
5.2.1. Work Activities<br />
The various work activities to be performed in the project are defined in the TMT Team’s Metric<br />
Program. The work activities are decomposed from project management task, support task, and<br />
product features into low-level tasks that expose all project risk factors and allow accurate<br />
estimate of resource requirements and schedule duration for each work activity.<br />
5.2.2. Schedule Allocation<br />
After defining the various work activities, the TMT PM schedules the work activities agreeing<br />
with the Table 1.1-2: Master Build Schedule and Table 1.1-1: <strong>Project</strong> Deliverables. The specific<br />
schedule allocations for the detailed tasks are defined in the TMT Team’s Metric Program.<br />
5.2.3. Resource Allocation<br />
The TMT PM allocates the various work activities to different team members based on their skill<br />
levels and desired roles stated in Figure 4.2-1: <strong>Project</strong> Internal Organization Structure and Table<br />
4.3-1: <strong>Project</strong> Roles and Responsibilities. The TMT PM and technical leads re-assesses resource<br />
allocations weekly (i.e., every Monday).<br />
5.2.4. Budget Allocation<br />
The Table 1.1-3: <strong>Project</strong> Budget Summary shows the budgets allocated to major work activities<br />
in the work breakdown structure. The detailed budget allocated to various tasks as well as other<br />
cost (e.g., travel, meeting, equipments, etc.) are specified in the TMT Team’s Metric Program.<br />
5.3. Control <strong>Plan</strong><br />
The key factors that contribute to the TMT project management are the processes of planning,<br />
scheduling, performance measurement, risk mitigation, variance analysis, and corrective action.<br />
The TMT PM coordinates with the different technical leads to develop the detailed plans based<br />
on established work assignments defined in the TMT Team’s Metric Program for the TMT<br />
project. Microsoft Office 2007 software is used to document the plans. The plans are then