Software Project Management Plan (SPMP) - Southern Polytechnic ...
Software Project Management Plan (SPMP) - Southern Polytechnic ...
Software Project Management Plan (SPMP) - Southern Polytechnic ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
5.3.2.3. Schedule Reviews<br />
Page 33 of 60<br />
Test <strong>Management</strong> Tool (TMT)<br />
<strong>Software</strong> <strong>Project</strong> <strong>Management</strong> <strong>Plan</strong> (<strong>SPMP</strong>)<br />
TMT-<strong>SPMP</strong>-1.2<br />
27-Sep-2010<br />
Schedule reviews are conducted by the TMT <strong>Project</strong> Advisor, PM, and technical leads on a<br />
weekly basis (i.e., every Mondays or Wednesdays). Applicable schedule updates upon reviews<br />
can be made to the TMT Team’s Metric Program; the updates are then notified to the client and<br />
all team members. Schedule reviews are done for at least one incremental release ahead to have<br />
early risk mitigation.<br />
5.3.2.4. Progress Variance Monitoring<br />
Actual progress can differ from the planned progress for many reasons, including but not limited<br />
to inaccurate effort estimation, resource limitation, plan and requirement changes, and etc. The<br />
TMT technical leads are responsible to notify the TMT PM and the PM is responsible to update<br />
the applicable scheduled tasks on the TMT Team’s Metric Program. Deviations that are beyond<br />
the PM’s capabilities to resolve (e.g., member drop outs, non-productive or poor performance,<br />
etc.) are brought to the <strong>Project</strong> Advisor’s attention.<br />
5.3.2.5. Progress Variance Resolution<br />
The TMT PM has the authority to reallocate resources, delegate and reschedule the tasks, or<br />
correct performance problems that are not impacting a major release. Otherwise, consultancies<br />
from the TMT Advisor are recommended.<br />
5.3.2.6. Follow-Up on Corrective Action<br />
The TMT Team’s Metric Program is used to identify the initial schedule deviation and to analyze<br />
the corrective action results. Corrective action items are closely monitored to ensure that they are<br />
effectively recovering the schedule variance before milestone or the master build schedule is<br />
jeopardized.<br />
5.3.3. Budget Control <strong>Plan</strong><br />
The total cost of the project is $140,000.00 spreading out to 14 weeks as shown in Table 1.1-3:<br />
<strong>Project</strong> Budget Summary. The project cost is calculated based on $100.00 per person-hour<br />
expended for each task by each assigned resource; i.e., $100.00 * effort hour * resource. Periodic<br />
cost analysis and reviews are conducted to assess performance and provide insight to the future<br />
task assignments.<br />
5.3.4. Quality Control <strong>Plan</strong><br />
There is no independent Quality Assurance (QA) Group under the TMT management. Instead,<br />
the TMT PM and Testing Group are responsible for assurance of all quality and production<br />
control requirements are being accomplished. The TMT Test Lead is responsible to conduct<br />
various reviews on project plans, requirements, designs, codes, tests, and all other documents. In<br />
performing these duties, the TMT Test Lead monitors adherence to all applicable policies,<br />
processes, procedures, and plans.