Kelly (1999b, p. 3 to 9) suggests that the key to managing the additional workload, identified from the maintenance plans, is by being<br />
both:<br />
• Effective in prioritising the list of outstanding work. Put another way, this is about how effective the maintenance department<br />
is in terms of deliverables of the maintenance strategy and providing plant reliability.<br />
• Pre-planning and executing the work in the most cost effective way. Again, put another way, this is about the maintenance<br />
department’s organisational efficiency.<br />
Going back to the above example of replacing the leaking seal within the gearbox or as another example replacing a bearing or oil<br />
as a result of the condition monitoring programs, Wireman (1990) suggests that these jobs can only be completed in the most cost<br />
effective and efficient manner by completing the steps depicted in the work flow diagram of Figure 6 (Kelly 1999b, p. 1-6).<br />
From the above is becomes obvious that the work flow system encompasses a number of steps and is not just about planning and<br />
scheduling.<br />
WORK PLANNING AND RESOURCE STRUCTURE<br />
As stated earlier, the overall objective in the pre-planning and execution of all work is to ensure that all work is handled in the most<br />
cost effective and efficient manner. To realise this objective the design of both the work planning system and resource structure<br />
should be aligned so as to match the different levels of work. Kelly and Riddell (2000, pp. 1-16 to 1-17) categorises all work into the<br />
following three levels:<br />
1. First line - usually follows the production operating pattern and its characteristics are that it is typically reactive and<br />
maintenance is required to (and should) respond quickly. This work should be resourced accordingly in terms of numbers,<br />
locations and shifts. For example, utilising shift trades as opposed to relying on call-ins (Kelly and Riddell 2000, p. 2-22).<br />
Similarly the work planning system’s centre of gravity should be aligned to this resource structure - i.e. the shift tradespeople<br />
/ shift supervisor should organise all necessary materials and information to enable a quick response to this work (Kelly<br />
1999b, pp. 1-7 to 1-11).<br />
2. Second line - work that has a longer lead time and can usually be held over to weekday shuts, weekends, etc. The work<br />
planning system’s centre of gravity should be aligned to a dedicated planner/s (Kelly 1999b, pp. 1-11 to 1-12). One reason for<br />
having dedicated planners is simply that it will increase the productivity (spanner time) of the trades by having the work<br />
planned and ready prior to execution. Peters (2003b, pp. 21 to 22) claims that the typical spanner time of trades in a reactive /<br />
unplanned environment is in the order of 30% to 40% (of an 8 hour day). Similarly the resource structure should be aligned so<br />
that the dedicated trades group only execute the second line work (Kelly and Riddell 2000, pp. 2-22 to 2-23). One of the pit falls<br />
of not being disciplined in relation to alignment of the different levels of work is that resources, both planners and trades, will<br />
naturally want to gravitate back toward executing the reactive work and the organisation will continue in the downward spiral<br />
of reacting as opposed to preventing the reactive work.<br />
3. Third line - work that is required to be carried out during major and/or full plant shuts such an annual Christmas campaigns,<br />
etc. The third line work planning system’s centre of gravity, like the second line work, should be aligned to a dedicated<br />
planner/s (Kelly 1999b, pp. 2-5 to 2-6). In saying this, the duration of shuts, size and type of work, etc will determine the need<br />
for a dedicated planner/s as opposed to the second line planner/s planning the third line work. The resource structure for the<br />
third line work would again depend on several factors such as timing (total plant shutdown as opposed to sections of the<br />
plant), duration of shuts, resources required (numbers, skills requirements), etc but in the main both the first and second line<br />
resources should be utilised and (if applicable) topped up via the use of contractors (Kelly and Riddell 2000, p. 2-23).<br />
INFORMATION DATA BASE / CMMS<br />
The information data base is the plant asset hierarchical library where all information should reside. Kelly (1999b, pp. 6-6 to 6-9)<br />
nominates that this information is inclusive of the following:<br />
• Manufacturers details (through Bills of Materials (BOM’s)).<br />
• History of all work performed.<br />
• Failure analysis data.<br />
• Cost to maintain.<br />
• Maintenance plan / schedule.<br />
• Spares.<br />
• Documentation - i.e. isolation plans, work instructions, drawings, etc.<br />
• Maintenance measures (MM’s) / Key Performance Indicators (KPI’s).<br />
A complete and accurate information data base increases the efficiency of planning and scheduling all work. The information data<br />
base exists whether or not organisations choose to invest in a computerised maintenance management system (CMMS). The<br />
objective of a CMMS is, put simply, the tool in which to transport each of the above functions so as to increase both the org a n i s a t i o n a l<br />
effectiveness and efficiency (Kelly 1999b, p. 8 -15).<br />