19.07.2013 Views

October - Library - Central Queensland University

October - Library - Central Queensland University

October - Library - Central Queensland University

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Kelly (1999b, p. 3 to 9) suggests that the key to managing the additional workload, identified from the maintenance plans, is by being<br />

both:<br />

• Effective in prioritising the list of outstanding work. Put another way, this is about how effective the maintenance department<br />

is in terms of deliverables of the maintenance strategy and providing plant reliability.<br />

• Pre-planning and executing the work in the most cost effective way. Again, put another way, this is about the maintenance<br />

department’s organisational efficiency.<br />

Going back to the above example of replacing the leaking seal within the gearbox or as another example replacing a bearing or oil<br />

as a result of the condition monitoring programs, Wireman (1990) suggests that these jobs can only be completed in the most cost<br />

effective and efficient manner by completing the steps depicted in the work flow diagram of Figure 6 (Kelly 1999b, p. 1-6).<br />

From the above is becomes obvious that the work flow system encompasses a number of steps and is not just about planning and<br />

scheduling.<br />

WORK PLANNING AND RESOURCE STRUCTURE<br />

As stated earlier, the overall objective in the pre-planning and execution of all work is to ensure that all work is handled in the most<br />

cost effective and efficient manner. To realise this objective the design of both the work planning system and resource structure<br />

should be aligned so as to match the different levels of work. Kelly and Riddell (2000, pp. 1-16 to 1-17) categorises all work into the<br />

following three levels:<br />

1. First line - usually follows the production operating pattern and its characteristics are that it is typically reactive and<br />

maintenance is required to (and should) respond quickly. This work should be resourced accordingly in terms of numbers,<br />

locations and shifts. For example, utilising shift trades as opposed to relying on call-ins (Kelly and Riddell 2000, p. 2-22).<br />

Similarly the work planning system’s centre of gravity should be aligned to this resource structure - i.e. the shift tradespeople<br />

/ shift supervisor should organise all necessary materials and information to enable a quick response to this work (Kelly<br />

1999b, pp. 1-7 to 1-11).<br />

2. Second line - work that has a longer lead time and can usually be held over to weekday shuts, weekends, etc. The work<br />

planning system’s centre of gravity should be aligned to a dedicated planner/s (Kelly 1999b, pp. 1-11 to 1-12). One reason for<br />

having dedicated planners is simply that it will increase the productivity (spanner time) of the trades by having the work<br />

planned and ready prior to execution. Peters (2003b, pp. 21 to 22) claims that the typical spanner time of trades in a reactive /<br />

unplanned environment is in the order of 30% to 40% (of an 8 hour day). Similarly the resource structure should be aligned so<br />

that the dedicated trades group only execute the second line work (Kelly and Riddell 2000, pp. 2-22 to 2-23). One of the pit falls<br />

of not being disciplined in relation to alignment of the different levels of work is that resources, both planners and trades, will<br />

naturally want to gravitate back toward executing the reactive work and the organisation will continue in the downward spiral<br />

of reacting as opposed to preventing the reactive work.<br />

3. Third line - work that is required to be carried out during major and/or full plant shuts such an annual Christmas campaigns,<br />

etc. The third line work planning system’s centre of gravity, like the second line work, should be aligned to a dedicated<br />

planner/s (Kelly 1999b, pp. 2-5 to 2-6). In saying this, the duration of shuts, size and type of work, etc will determine the need<br />

for a dedicated planner/s as opposed to the second line planner/s planning the third line work. The resource structure for the<br />

third line work would again depend on several factors such as timing (total plant shutdown as opposed to sections of the<br />

plant), duration of shuts, resources required (numbers, skills requirements), etc but in the main both the first and second line<br />

resources should be utilised and (if applicable) topped up via the use of contractors (Kelly and Riddell 2000, p. 2-23).<br />

INFORMATION DATA BASE / CMMS<br />

The information data base is the plant asset hierarchical library where all information should reside. Kelly (1999b, pp. 6-6 to 6-9)<br />

nominates that this information is inclusive of the following:<br />

• Manufacturers details (through Bills of Materials (BOM’s)).<br />

• History of all work performed.<br />

• Failure analysis data.<br />

• Cost to maintain.<br />

• Maintenance plan / schedule.<br />

• Spares.<br />

• Documentation - i.e. isolation plans, work instructions, drawings, etc.<br />

• Maintenance measures (MM’s) / Key Performance Indicators (KPI’s).<br />

A complete and accurate information data base increases the efficiency of planning and scheduling all work. The information data<br />

base exists whether or not organisations choose to invest in a computerised maintenance management system (CMMS). The<br />

objective of a CMMS is, put simply, the tool in which to transport each of the above functions so as to increase both the org a n i s a t i o n a l<br />

effectiveness and efficiency (Kelly 1999b, p. 8 -15).<br />

65

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!