Supply, installation, testing and commissioning of pcs and ... - GAIL
Supply, installation, testing and commissioning of pcs and ... - GAIL
Supply, installation, testing and commissioning of pcs and ... - GAIL
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
17.5.2 A bid determined as substantially non-responsive will be rejected by the OWNER <strong>and</strong> may<br />
not subsequently be allowed by the OWNER to be made responsive by the bidder by<br />
correction <strong>of</strong> the non-conformity.<br />
17.5.3 Bidder’s Bid shall be considered non-responsive <strong>and</strong> rejected, if deviations are taken to the<br />
under mentioned provisions <strong>of</strong> Bid Documents by the Bidder:-<br />
7<br />
i. Bid Security as per Article 9, Section 2.<br />
ii. Performance Security (CONTRACT Performance Bank Guarantee) for less than 10%<br />
<strong>of</strong> Contract/Order value.<br />
iii. Period <strong>of</strong> validity <strong>of</strong> bids as per Article 10 Section 2.<br />
iv. Force Majeure as per Section 3<br />
v. Resolution <strong>of</strong> Dispute/Arbitration as per Section-3<br />
vi. Completion period.<br />
vii. Termination <strong>of</strong> Contract (Provision as per Section-3)<br />
viii. Any other such provisions if specifically stipulated elsewhere in the Bid Document.<br />
17.5.4 Bids not conforming to Scope <strong>of</strong> Work as mentioned in Bid Document will be rejected.<br />
17.5.6 Conditional Bids will be liable for rejection.<br />
18.0 ARTICLE - 18: OPENING OF PRICE BIDS<br />
The price bids <strong>of</strong> the substantially responsive bidders will be opened later. The price bids <strong>of</strong><br />
those bidders determined to be not substantially responsive will be rejected.<br />
19.0 ARTICLE - 19: COMPARISON OF BIDS<br />
19.1 The OWNER will evaluate <strong>and</strong> compare bids previously determined to be substantially<br />
responsive.<br />
19.2 Arithmetical errors will be rectified on the following basis:-<br />
If there is a discrepancy between the unit price <strong>and</strong> the total price that is obtained by<br />
multiplying the unit price <strong>and</strong> quantity, the unit price shall prevail <strong>and</strong> the total price will be<br />
corrected. If there is a discrepancy between the total amount <strong>and</strong> the sum <strong>of</strong> total prices, the<br />
sum <strong>of</strong> the total prices shall prevail <strong>and</strong> the total bid amount will be corrected.<br />
19.3 OWNER’s evaluation <strong>and</strong> comparison <strong>of</strong> prices <strong>of</strong> previously determined substantially<br />
responsive bids shall take following in account:<br />
The evaluated price <strong>of</strong> bidders shall include the:<br />
i) Total contract price as per the Schedule <strong>of</strong> Rates (SOR).<br />
19.3.1 Comparison <strong>of</strong> Bids will be on the basis <strong>of</strong> overall lowest cost to <strong>GAIL</strong> as detailed in the<br />
Scope <strong>of</strong> Work.