j. Verify backup time on full load on the UPS<br />
4.0 PLACEMENT OF ORDER<br />
<strong>GAIL</strong> shall place the PO on the short listed Bidder. <strong>GAIL</strong> also reserves the right<br />
to reject any or all the bids without assigning any reason what so ever.<br />
After placing the FOI, the vendor shall submit the detailed Project Schedule to<br />
the Engineer-In-Charge stating the dates <strong>and</strong> activities planned including the<br />
details <strong>of</strong> the engineers that will be deployed for the <strong>installation</strong> <strong>and</strong><br />
configuration <strong>of</strong> the PCs <strong>and</strong> associated peripherals.<br />
5.0 SITE READINESS<br />
5.1 Site Preparation<br />
The site for <strong>installation</strong> <strong>of</strong> the equipment/materials shall be provided by<br />
<strong>GAIL</strong> for the <strong>installation</strong> <strong>of</strong> equipments along with the power supply up<br />
to the point <strong>of</strong> UPS (Indian style 5 AMP power socket will be provided).<br />
5.2 Inspection/Acceptance Testing<br />
QAPLUS tests shall be run for CPU, RAM, hard disk, floppy drive <strong>and</strong><br />
result should confirm to the Diagnostic report, submitted by the Bidder.<br />
5.3 Acceptance Test at <strong>GAIL</strong> Offices<br />
On completion <strong>of</strong> <strong>installation</strong> <strong>of</strong> the equipment but before<br />
<strong>commissioning</strong> by the SUPPLIER, each item <strong>of</strong> the equipment shall be<br />
physically inspected on-site jointly by <strong>GAIL</strong> <strong>and</strong> Bidder for the<br />
correctness <strong>and</strong> the completeness <strong>of</strong> the <strong>installation</strong> <strong>and</strong> acceptability<br />
for start-up.<br />
The acceptance test, which involves the operation <strong>of</strong> the complete<br />
system, will be conducted by the Bidder in the presence <strong>of</strong> the <strong>GAIL</strong><br />
representative. The system will be accepted subject to the compliance<br />
<strong>of</strong> the tests to the satisfaction <strong>of</strong> <strong>GAIL</strong>.<br />
In case <strong>of</strong> failures, the acceptance tests will be restarted provided the<br />
maximum number <strong>of</strong> restarts shall not exceed two in number. System<br />
failing in final acceptance test is likely to be rejected <strong>and</strong> would require<br />
replacement immediately.<br />
In case the vendor found to be supply the items not as per the quoted<br />
specifications, EIC has a right to reject the material at site(s) <strong>and</strong><br />
vendor shall be responsible for replacement <strong>of</strong> the same without any<br />
cost <strong>and</strong> time implications. The final payment for the same shall be<br />
released after resolution <strong>of</strong> all identified problems.<br />
5.4 Acceptance <strong>of</strong> S<strong>of</strong>tware