the Southern Access Road where the site is split.<br />

<strong>BAE</strong> <strong>SYSTEMS</strong> <strong>PLC</strong><br />

<strong>ROF</strong> <strong>BISHOPTON</strong><br />

<strong>Traffic</strong> <strong>Management</strong> <strong>Plan</strong><br />

24 th October 2010<br />

This will allow all private and light commercial vehicles to remain within the<br />

“clean” zone outwith the security line and thus avoid the need for cleaning of<br />

these vehicles prior to leaving site.<br />

Generally <strong>BAE</strong> Systems and associated works contractors will provide a range<br />

of dedicated on site vehicles for use within the main site only. This range will<br />

include:-<br />

4WD Pickups / Station Wagon’s<br />

8 wheel tippers<br />

Light commercial vans / Pickups<br />

Crew buses<br />

Hiabs<br />

Agricultural Tractors & Trailers<br />

Articulated Dump Trucks (Moxy’s)<br />

360 0 excavators<br />

Dozers & Scrapers<br />

Front loaders<br />

It is envisaged that this onsite fleet is sufficient to undertake the works, manage<br />

deliveries and provide personnel transfer between the Reception Centre and<br />

the main site compound. Provision will be enhanced as required to suit usage<br />

demand during the entire works programme.<br />

Any vehicle transiting between main site remediation / construction zones and<br />

through security to the public highway is required to first pass through a<br />

wheelwash facility. This process will be managed by the logistics contractor by<br />

means of filter lane provision to direct vehicles through the wheelwash as a<br />

default movement.<br />

All vehicles carrying bulk loose material i.e. tippers etc. will require automatic<br />

load covers to be deployed prior to leaving the point of loading and transiting<br />

the site to the public road network.<br />

These vehicles will be held at outbound security for weighing, checking of<br />

transit documentation and confirmation that wheels are clean and loads have<br />

been covered prior to leaving site.<br />

Large Commercial vehicles will largely be involved in the following movements<br />

Delivery of plant and equipment at the outset of the project<br />

Delivery of bulk consumables associated with earthworks and landfill<br />

construction<br />

Delivery of materials associated with the construction of the Southern<br />

Access Road (south)<br />

Removal from site of waste materials for recycling e.g. metals from<br />

demolition<br />

Removal from site of surplus clean material to market i.e. surplus hardcore,<br />

topsoil’s or other valuable waste.<br />

Relocation of limited useable material from the main site to SAR (North<br />

Sector)<br />

Relocation of limited useable material from the main site to the M8 Junction<br />

GARDINER & THEOBALD LLP 19