FAULT FINDING CHART 5<br />
Does burner flame<br />
modulate ?<br />
No<br />
Yes<br />
Normal operation<br />
Release the hermetic chamber cover by removing<br />
two screws on both sides and by lifting them to<br />
release from their retaining hooks. ( Figure 26)<br />
RETAINING<br />
LUGS<br />
Chwck wiring from<br />
PCB to modulation<br />
coil on gas valve<br />
Yes<br />
Replace gas valve<br />
INNER<br />
CASING<br />
PANEL<br />
No<br />
Replace PCB<br />
Figure 26<br />
18. Routine Servicing<br />
VIEWING<br />
WINDOW<br />
22<br />
SERVICE PROCEDURE<br />
1. Remove the outer case as outlined in section“Replacing Components”<br />
2. Visually check all joints for gas/water tightness.<br />
3. Visually inspect the flue system.<br />
4. Check the condition of the seals around the combustion chamber.<br />
5. Check condition of electrodes and their location.<br />
6. Conduct a flue gas analysis of CO/CO2 ratio to confirm the combustion<br />
gas ratio is less that 0.004. If not check the combustion chamber and<br />
flue system for signs of leakage,damage or blockage. Remove any<br />
obstruction and clean as necessary. If clear check burner pressures,<br />
injectors or gas valve settings. Adjust and clean as necessary.<br />
18.1 To ensure the continued efficient and safe<br />
operation of the boiler it is recommended that it is<br />
checked and serviced regularly. The servicing must be<br />
carried out by a competent person in accordance with<br />
the Gas Safety (Installation and Use) Regulations. The<br />
frequency of servicing will depend upon the particular<br />
installation conditions and usage, but in all cases the<br />
boiler must be serviced at least once a year.<br />
18.2 Following servicing of the boiler the relevant<br />
sections of the 'Benchmark' Installation,<br />
Commissioning and Servicing Log Book must be<br />
completed.<br />
18.3 Prior to servicing a check of the flue operation<br />
and terminal guard (if fitted) along with a preliminary<br />
check of the boilers operation must be undertaken.<br />
18.4 Ensure the boiler is cold and that both the<br />
electrical and gas supplies to the boiler are isolated<br />
before commencing service of the boiler.<br />
18.5 Remove the boiler casing as follows:<br />
Open the front panel by removing two screws at<br />
the bottom of the boiler, Figure <strong>25</strong>.<br />
Release the side panels by removing the screws on<br />
the upper and lower sides (Figure 27 ). Remove the<br />
panels by swinging them out and lifting them up.<br />
Figure 27<br />
1<br />
2<br />
SECURING<br />
SCREWS<br />
(4 OFF)<br />
18.6 Remove the combustion chamber cover by<br />
removing four screws on sides. (Figure <strong>28</strong>)<br />
SECURING<br />
SCREWS (6 OFF)<br />
SECURING<br />
SCREWS<br />
SIDE PANELS<br />
Figure <strong>25</strong><br />
Figure <strong>28</strong><br />
SECURING<br />
SCREWS<br />
Page 22<br />
COMBUSTION<br />
CHAMBER<br />
COVER<br />
VIEWING<br />
WINDOW