Installation Instructions - KACO new energy, Inc.
Installation Instructions - KACO new energy, Inc.
Installation Instructions - KACO new energy, Inc.
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Installing the Inverter<br />
Authorised electrician<br />
7.3.2.3 Recommended standard connection<br />
Equal MPP voltages must be applied to input 1 and 2, as well as inputs 3 and 4. The MPP voltages of the two DC<br />
paths can be different. They are tracked by separate, independently operating MPP trackers (MPP trackers A and B).<br />
(n 1<br />
=n 2<br />
, n 3<br />
=n 4<br />
).<br />
Electrical data for standard connection<br />
Connection of the DC inputs Number of modules per string n 1<br />
=n 2<br />
, n 3<br />
=n 4<br />
P max<br />
I max<br />
per string < 6 kW<br />
MPP trackers A+B together < 12 kW<br />
< 18.6 A per tracker<br />
MPP tracker A<br />
MPP tracker B<br />
U MPP<br />
= 350 - 800 V<br />
U MPP<br />
= 350 - 800 V<br />
n 1<br />
= n 2<br />
n 3<br />
= n 4<br />
Figure 8: Recommended standard connection<br />
7.3.2.4 Parallel input connection<br />
The DC inputs can also be connected in parallel. Only strings with identical MPP voltage can be connected in<br />
parallel (n 1<br />
=n 2<br />
=n m<br />
).<br />
The maximum input current rises to 37.2 A for parallel connection.<br />
In case of a parallel input connection, MPP trackers A and B must be bridged. If input 1 is connected to input 2 and<br />
input 3 is connected to input 4, then there is no parallel operation and the maximum input current continues to be<br />
18.6 A. Parallel operation is automatically recognized by the inverter.<br />
Page 20 <strong>Installation</strong> <strong>Instructions</strong> blueplanet XP10U-H4