01.05.2014 Views

CEMP - NZ Transport Agency

CEMP - NZ Transport Agency

CEMP - NZ Transport Agency

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>NZ</strong> <strong>Transport</strong> <strong>Agency</strong><br />

CSM2 & MSRFL<br />

It is anticipated that there will be approximately 85,000m³ of excavated (cut to waste) material that<br />

is deemed unsuitable for construction. For the most part, this material will be disposed of on site,<br />

reducing haulage distances.<br />

1.3.6 Bridges and retaining walls<br />

The construction of the nine bridges and associated retaining walls for the interchanges, overpasses<br />

and underpasses will be a significant part of the Project. Bridge components such as deck beams<br />

(both concrete and steel) will be manufactured in a controlled environment at an off-site facility.<br />

Other components will be cast in-situ using local ready mixed concrete providers. Both piled and<br />

spread footing bridge foundations will be used, with piles likely be either bored concrete or H-steel<br />

sections.<br />

1.3.7 Utilities<br />

There are several utilities that will need relocation, amendment or protection throughout the<br />

project. Each utility provider has been consulted to understand the various requirements and<br />

limitations in the local area that may impact relocation or protection of the services. These include:<br />

• Transpower’s Islington to Springston 66 kV transmission lines to the southwest of the<br />

Shands Road and Marshs Road intersection where the alignment falls within the<br />

transmission line clearance envelope;<br />

• Orion’s overhead electricity supply network;<br />

• Chorus and Telstra Clear telecommunications networks;<br />

• Water supply and wastewater disposal networks;<br />

• Water Races.<br />

The necessary written approvals and agreements to enable the works will need to be obtained at a<br />

future stage, where required.<br />

1.3.8 Stormwater<br />

Surface water will be dealt with differently in the MSRFL and CSM2 alignments. Main South Road<br />

and the adjacent rail embankment have impediments to overland flows, and they have little<br />

stormwater infrastructure in place. The widening of Main South Road will have little impact on the<br />

current behaviour of the catchment. Therefore, isolated soak pits in the low lying areas are<br />

proposed, with allowances for potential over topping.<br />

For the CSM2 section at low points in the topography of the area, the surface water flood flows will<br />

pass underneath the motorway using a series of siphons. Bunds will protect the roadside swales<br />

and dispersal points. The additional disposal areas at locations of concentrated overland flows will<br />

provide protection to the road against flooding. Stockwater races will be passed under the<br />

motorway via a siphon system, typically measuring between 300mm and 450mm.<br />

There are nine existing stockwater races, two along MSRFL and seven along CSM2, noting that a<br />

stockwater race runs parallel to MSRFL on the South Eastern side within the road reserve for<br />

approximately 2100m. These will be subject to alterations, including crossings under the<br />

Draft 11 <strong>CEMP</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!