CEMP - NZ Transport Agency
CEMP - NZ Transport Agency
CEMP - NZ Transport Agency
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>NZ</strong> <strong>Transport</strong> <strong>Agency</strong><br />
CSM2 & MSRFL<br />
It is anticipated that there will be approximately 85,000m³ of excavated (cut to waste) material that<br />
is deemed unsuitable for construction. For the most part, this material will be disposed of on site,<br />
reducing haulage distances.<br />
1.3.6 Bridges and retaining walls<br />
The construction of the nine bridges and associated retaining walls for the interchanges, overpasses<br />
and underpasses will be a significant part of the Project. Bridge components such as deck beams<br />
(both concrete and steel) will be manufactured in a controlled environment at an off-site facility.<br />
Other components will be cast in-situ using local ready mixed concrete providers. Both piled and<br />
spread footing bridge foundations will be used, with piles likely be either bored concrete or H-steel<br />
sections.<br />
1.3.7 Utilities<br />
There are several utilities that will need relocation, amendment or protection throughout the<br />
project. Each utility provider has been consulted to understand the various requirements and<br />
limitations in the local area that may impact relocation or protection of the services. These include:<br />
• Transpower’s Islington to Springston 66 kV transmission lines to the southwest of the<br />
Shands Road and Marshs Road intersection where the alignment falls within the<br />
transmission line clearance envelope;<br />
• Orion’s overhead electricity supply network;<br />
• Chorus and Telstra Clear telecommunications networks;<br />
• Water supply and wastewater disposal networks;<br />
• Water Races.<br />
The necessary written approvals and agreements to enable the works will need to be obtained at a<br />
future stage, where required.<br />
1.3.8 Stormwater<br />
Surface water will be dealt with differently in the MSRFL and CSM2 alignments. Main South Road<br />
and the adjacent rail embankment have impediments to overland flows, and they have little<br />
stormwater infrastructure in place. The widening of Main South Road will have little impact on the<br />
current behaviour of the catchment. Therefore, isolated soak pits in the low lying areas are<br />
proposed, with allowances for potential over topping.<br />
For the CSM2 section at low points in the topography of the area, the surface water flood flows will<br />
pass underneath the motorway using a series of siphons. Bunds will protect the roadside swales<br />
and dispersal points. The additional disposal areas at locations of concentrated overland flows will<br />
provide protection to the road against flooding. Stockwater races will be passed under the<br />
motorway via a siphon system, typically measuring between 300mm and 450mm.<br />
There are nine existing stockwater races, two along MSRFL and seven along CSM2, noting that a<br />
stockwater race runs parallel to MSRFL on the South Eastern side within the road reserve for<br />
approximately 2100m. These will be subject to alterations, including crossings under the<br />
Draft 11 <strong>CEMP</strong>