Appendix A: <strong>Infrastructure</strong> Schedule<br />

29 February 2012<br />

<strong>Bristol</strong> <strong>Development</strong> <strong>Framework</strong><br />

<strong>Infrastructure</strong> <strong>Delivery</strong> <strong>Programme</strong><br />

Greater <strong>Bristol</strong> Bus Network: A4018 <strong>Bristol</strong> to Cribbs Causeway (Corridor 2).<br />

Major improvements to bus corridors and the purchase of new buses. Physical measures include bus priority measures and improved bus<br />

stops with new shelters, raised kerbs and, at the most heavily used stops, Real Time Passenger Information.<br />

Transport <strong>Infrastructure</strong><br />

Essential<br />

Works proposed within <strong>Bristol</strong> for this corridor include new bus lanes in the Whiteladies Road and Westbury Road areas, signal<br />

improvements at the Blackboy Hill gyratory, improved lining and signing in the Clifton Triangle and bus stop improvements. Work<br />

completed to date includes the purchase of 30 new buses by First for services 1 and 54. Outside <strong>Bristol</strong>, work completed to date includes<br />

the construction of a new bus lane along Lysander Road, Cribbs Causeway and new buses have also been introduced along the corridor.<br />

Work currently in progress.<br />

Overall project programmed for completion by 2012.<br />

[Source: Major Scheme Bid]<br />

Cost: Funding Sources: Phasing:<br />

£69.8m for overall project<br />

£42.3m DfT (approved)<br />

£20m First<br />

£5.7m developer contributions<br />

£1.8m local authority contributions<br />

2006‐2016<br />

Risks:<br />

Contingencies:<br />

Relevant Policy Areas:<br />

City Centre<br />

Northern Arc<br />

Rest of <strong>Bristol</strong><br />

Outside <strong>Bristol</strong><br />

Lead Agencies:<br />

West of England Partnership<br />

First Group<br />

‐ Page 4 of 41 ‐