Version 6/19/12<br />

PART 2 – PRODUCTS<br />

Not used<br />

PART 3 - EXECUTION<br />

3.01 PREPARATION<br />

A. Refer to Public Works Construction <strong>Standards</strong>, NCTCOG, 4 th Edition, Item 203.1, 203.2 and<br />

203.3.<br />

PART 4 - MEASUREMENT AND PAYMENT<br />

4.01 MEASUREMENT<br />

A. This Item shall be measured on a Lump Sum (LS) basis, unless indicated otherwise and shall<br />

include the removal <strong>of</strong> all items within the limits <strong>of</strong> construction not specifically called out<br />

to remain.<br />

B. Removal <strong>of</strong> existing pavement will be measured separately and paid for by the square yard<br />

(SY), regardless <strong>of</strong> thickness and type. Concrete curb and gutter removal will not be<br />

measured separately and is considered subsidiary to this item.<br />

C. Removal <strong>of</strong> existing sidewalk and ramps will be measured separately and paid for by the<br />

square yard (SY), regardless <strong>of</strong> thickness and type.<br />

D. Removal <strong>of</strong> existing inlets, headwalls, manholes, etc. will be measured separately and paid<br />

for per each (EA) inlet removed, regardless <strong>of</strong> the size <strong>of</strong> the existing inlet. Removal <strong>of</strong><br />

existing pipe will not be measured separately and is considered subsidiary to this item.<br />

4.02 PAYMENT<br />

A. All work performed and materials furnished in accordance with this Item will be paid for at<br />

the unit bid price. This price is full compensation for all material, labor, equipment, tools<br />

and superintendence necessary to complete the work.<br />

END OF SECTION<br />

<strong>City</strong> <strong>of</strong> <strong>Frisco</strong> May 2012<br />

Standard Technical Specification General Site Preparation 024100-2