11.10.2014 Views

Alternative Project Delivery - Texas Water Development Board

Alternative Project Delivery - Texas Water Development Board

Alternative Project Delivery - Texas Water Development Board

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Section 2<br />

Key Contractual Issues<br />

A DB contract is primarily based on delivering an asset that was defined by the<br />

Owner’s <strong>Project</strong> Criteria for a lump sum fixed price or guaranteed maximum price.<br />

A DB contract generally provides that design activities and certain construction<br />

activities can be performed concurrently. Consequently, a DB contract is structured to<br />

consider the schedule and project cost implications of all permits that will be required<br />

to commence construction. The requirements and obligations of the Owner and the<br />

DB Contractor concerning the development, review, submission, and approval of<br />

project permits are usually explicitly addressed as part of a DB contract.<br />

The Owner may utilize an Owner's Representative or Construction Manager to<br />

ensure that the DB Contractor constructs the project consistent with the requirements<br />

of the DB contract. The Design Consultant of the DB Contractor is the Designer of<br />

record for the project. Upon completion of construction and the meeting of<br />

commercial operational requirements, final payment is authorized to the DB<br />

Contractor by the Owner. The facility is turned over to the Owner and commences<br />

operation with the Owner’s operator.<br />

Benefits<br />

There are a set of benefits that may result from the close cooperation and teaming of<br />

the Design Consultant and the Construction Contractor as part of a DB contract.<br />

The single-point accountability reduces the potential for disputes between the Design<br />

Engineer and the Construction Contractor. A concurrent cooperative effort<br />

between the DB team’s Design Consultant and the Construction Contractor can<br />

benefit the project by shortening the project’s schedule and/or reducing the capital<br />

costs. Examples of this may occur when the Construction Contractor works with<br />

the Design Consultant to identify lower cost construction alternatives than what the<br />

Design Consultant selected. The shared DB team’s incentive to produce a project<br />

that meets the Owner's requirements while being cost competitive, often leads to<br />

design innovations. Even without significant changes to the project’s installed<br />

material and equipment, the concurrent implementation of the design and permitting<br />

activities with the pre-construction work (i.e., site preparation, temporary utilities,<br />

access road construction) can shorten the project’s overall schedule. A shortened<br />

project schedule may result in lower project cost.<br />

In DB project delivery, the contracted price to design and build the project is<br />

established at an earlier point in the project than with a traditional DBB approach. In a<br />

DBB, the design is completed and the project permitted before the construction bid is<br />

generally available.<br />

Areas of Concern<br />

The primary area of concern for DB, and other alternative delivery approaches, is that<br />

current laws regulating public sector design and construction were promulgated<br />

without consideration of DB or DBO-type approaches. Consequently, the legal basis<br />

for the use of these methods of project delivery is frequently unclear, limited or even<br />

precluded. Specifically, selecting Design Engineers and Construction Contractors<br />

jointly based on costs and qualifications is perceived as both controversial and<br />

2-8 <strong>Texas</strong> <strong>Water</strong> <strong>Development</strong> <strong>Board</strong> B1381-Sect2

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!