Appendix A<br />

EPC: Engineer-Procure-Construct project delivery method.<br />

- L -<br />

Life Cycle <strong>Project</strong> Costs: The estimated total project capital and operational costs<br />

associated with a project throughout the useful life of the project.<br />

- O -<br />

Operator: A firm or business organization that operates a project facility or facilities.<br />

Owner: An individual or entity that owns a real property and/or a facility.<br />

Owner’s Agent: A consulting firm that is retained by an Owner to prepare or assist<br />

with the preparation of procurement documents (RFQs, RFPs, <strong>Project</strong> Criteria,<br />

contracts) in order to implement an alternative project delivery.<br />

Owner's Representative: A firm with the expertise and resources to provide the<br />

construction phase engineering services, construction monitoring and contract<br />

administration, and other construction oversight services of project on behalf of the<br />

Owner.<br />

- P -<br />

Performance Guarantee: An assurance of the quality or the length of use to be<br />

expected from a product or facility offered for sale often with a promise of<br />

reimbursement.<br />

Procurement Advisor: A consulting firm that provides guidance and assistance to an<br />

Owner for selection, development and execution of a procurement for a facility via an<br />

alternative project delivery method. The Procurement Advisor can act solely in an<br />

advisory role or as the Owner’s Agent.<br />

<strong>Project</strong> Criteria: The basis of design, design criteria, engineering drawings,<br />

diagrams, performance specifications and other information that are used to define the<br />

Owner’s project requirements.<br />

<strong>Project</strong> Guarantor: A firm that is a DBO Contractor project participant or an<br />

affiliated company that pledges a financial performance guarantee for a project. The<br />

<strong>Project</strong> Guarantor accepts responsibility for fulfilling the obligations of the entire<br />

project.<br />

- R -<br />

Resident Engineer: An individual permanently assigned at a job site for the purpose<br />

of representing the Owner’s interests during the construction phase, including<br />

providing an official examination or review of the work completed.<br />

RFP: Request for Proposal.<br />

RFQ: Request for Qualifications.<br />

A-2 <strong>Texas</strong> <strong>Water</strong> <strong>Development</strong> <strong>Board</strong> B1381