Development of Architectural and Engineering Designs<br />

Using the schedule prepared by the Employer in the TOR, the Consultant shall produce<br />

architectural and engineering designs, details, specifications and cost estimates <strong>for</strong><br />

comments and recommendations from the Employer. After incorporating the comments<br />

in the schematic designs and adjusting the estimates, produce structural (calculations,<br />

drawings .etc), electro-mechanical (layouts, calculations, drawings, details and<br />

specification) to be finalized and discussed with the Employer and estimated cost to be<br />

reviewed.<br />

The drawings shall include but not limited to the site location, site plans, floor plans,<br />

sections, and elevations, perspectives and models <strong>for</strong> all buildings. The drawings shall be<br />

presented in appropriate scales.<br />

Task 3- The Consultant is to prepare detailed design drawings, technical<br />

specifications and bill of quantities <strong>for</strong> each component of the project to the level of<br />

detail normally required <strong>for</strong> internationally financed projects and should be enough<br />

readable without causing any conflict.<br />

During the design of the project, the Consulting Firm is to consider the appropriate<br />

number of implementation contracts, interfaces and coordination required to execute each<br />

contract without conflict between contractors implementing the works. A thorough study<br />

of the local contacting firms should be developed and accordingly the project packages<br />

will be devised in number that match the local capabilities in implementation.<br />

The Consulting Firm is to produce individual report and documentation accordingly.<br />

Task 4- After consultations between <strong>UNDP</strong>/PAPP and Consulting Firm on the<br />

Packaging of contracts <strong>for</strong> bidding, the Consultant is to prepare tender documents <strong>for</strong><br />

individual components of the project. The tender documents shall consist of:<br />

1- Bill of Quantities including preambles.<br />

2- Drawings<br />

3- Technical Specifications (General & Special)<br />

4- Detailed Priced B.O.Q<br />

5- Supplementary In<strong>for</strong>mation.<br />

6- Cost estimates of each entity and the overall estimate of the project.<br />

All above mentioned documents should be submitted in hard and soft copies (4 copies).<br />

Task 5- The consultant shall conduct thorough survey of all existing utilities and coordinate with<br />

Municipality of Beit lahia as well as Coastal Municipal Water Utility (CMWU) to<br />

identify road levels bench marks, planned schemes <strong>for</strong> utilities …etc. The consultant shall<br />

be responsible <strong>for</strong> coordinating <strong>for</strong> electricity and telecommunication services with<br />

concerned parties and identify the needs in connection with the project necessary relevant<br />

services. The consultant will develop the landscaping design of the residential<br />

neighborhood respecting social aspects, needs of disabled, special community needs such<br />

that to have environment friendly features of the neighborhood.<br />

Task 6- The Consulting Firm is to prepare engineering and other documents necessary <strong>for</strong><br />

obtaining construction licenses from related authorities, and to insure that this project can<br />

be accepted <strong>for</strong> approval by the concerned departments.<br />

Also he shall submit the final assignment report which will cover the architectural, civil,<br />

electrical and mechanical design reports along with the cost analysis.<br />

26