6. Sump tank<br />
The sump tank allows draining liquid fuel from combustion system and from<br />
exhaust plenum when there is false start. It may be preassembled and includes<br />
the followings<br />
-One tank of 1 m 3 capacity<br />
-One manual pump<br />
Gas Fuel System<br />
FUEL GAS HANDLING FACILITIES<br />
SCOPE OF WORK<br />
The Contractor shall design, manufacture, inspect, test, delivery to the site and<br />
install of natural gas handling facilities with all accessories as specified hereunder<br />
for the plant.<br />
The gas turbine unit shall be furnished with a complete gas fuel system. The gas<br />
handling system including Gas Booster Compressor shall also be provided.<br />
NATURAL GAS SUPPLY SYSTEM<br />
To forward the natural gas from the main gas supply header to the gas turbine<br />
unit and to adjust its supply pressure to normal operating pressure, the<br />
Contractor shall furnish one (1) complete factory assembled skid mounted gas<br />
pressure regulating unit including all accessories and necessary pipe connections<br />
to the BOARD's gas supply header for gas turbine unit.<br />
Each gas handling unit shall comprise at least the following major items:<br />
Gas Booster Compressors (one running and one standby, each having capacity for<br />
meeting total gas requirement at all ambient temperatures with 10% margin)<br />
with necessary sealing, cooling, anti-surge device, proven control system etc.<br />
Inlet strainer<br />
A flow meter with bypass system and with integration<br />
Pressure gauges<br />
Pressure regulating equipment<br />
Safety valve and relief valve<br />
A gas conditioner (scrubber, separator and others as required)<br />
Other equipment for satisfactory completion of the work.<br />
Each unit shall have guaranteed capacity, which matches or exceeds the gas<br />
turbine needs under all load operating conditions at site conditions.<br />
Specification of natural gas is shown on Appendix (Vol 2 of 3)<br />
3.3.2.8 Air Inlet System<br />
The air filtration arrangement shall be multi stage (pre-filter and high efficiency).<br />