Verlorenvlei Estuary Management Plan<br />
Part 3: Detailed Implementation Plans<br />
3.8 Funding Sources and Opportunities<br />
3.8.1 Targets & Critical Limits<br />
Operational specifications refer to the measureable targets or critical limits applicable to<br />
activities/developments or activity/development zones in and around the estuary.<br />
To be included in later version of EMP by the Estuary Forum Executive team<br />
3.8.2 Management Strategies and Actions<br />
The following actions or issues, specifically related to funding sources and opportunities have been<br />
identified at the Stakeholder Workshop held in Eland Bay (September 2009):<br />
<br />
Generate/source funding to implement the EMP. Financing (funding and budgets) need to<br />
be in the short- and the long-term, e.g. Biosphere funded local community projects.<br />
In order to address the above issues the following actions are proposed:<br />
ACTION 8.1: Prepare a financial plan for the implementation of the Verlorenvlei EMP<br />
Related Strategic<br />
Objective/s<br />
Cross-cutting to all objectives<br />
National <strong>Environmental</strong> Management: ICM Act (No 24 of 2008)<br />
Relevant legislation<br />
Local Government: Municipal Systems Act (No 32 of 2000)<br />
National water Act (No 36 of 1998)<br />
Conservation of Agricultural Resources Act (No 43 of 1983)<br />
Responsible agent<br />
Estuary Forum together with government departments (DEA, DWA, DAFF, District and<br />
local municipality) and other institutions (e.g. CapeNature) and business in the area<br />
Estimated Budget R50 000<br />
Timeframe<br />
1 year<br />
Priority<br />
High<br />
3.8.3 Detailed Management Action Plans for Priority Actions<br />
Once the priority actions have been identified, the appointed Technical Working Groups (or liaison<br />
teams) will be required to prepare detailed management action plans for these actions. A template<br />
for the preparation of MAPs is as follows:<br />
ACTION ……<br />
Requirements stipulated in policy<br />
and legislation<br />
Available methods, protocols and<br />
best practice-guides<br />
Operational Specifications/<br />
Links to EZP<br />
Detailed work plan<br />
Scheduling<br />
Responsibilities<br />
Monitoring plan<br />
Human Resource Plan<br />
Financial Resource Plan<br />
………………………<br />
Page 3-4