29.01.2015 Views

STUDY SUMMARY - IPMU

STUDY SUMMARY - IPMU

STUDY SUMMARY - IPMU

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>SUMMARY</strong> REPORT<br />

WIDE FIELD FIBER-FED OPTICAL<br />

MULTI-OBJECT SPECTROMETER (WFMOS)<br />

telescope environment and interfaces in critical locations and/or simple measurements to<br />

characterize the local environments.<br />

5. Some spectrograph gratings do not meet the delivery date. This schedule assumes<br />

delivery of all gratings is in time for integration and test. Sufficient testing and early<br />

integration can be done with a low-spec grating and/or a single accepted grating.<br />

6. Positioner Contractor unable to Perform. This acknowledges a single source for a critical<br />

deliverable. Mitigate with close monitoring and supplement with JPL resources if needed.<br />

This approach has been used often in the past with good success.<br />

7. Spectrograph aspherics difficult to manufacture. This risk is listed because only verbal<br />

quotes have been obtained from the vendors. It is expected to be addressed quickly by<br />

seeking alternate vendors as well as active involvement and management of the selected<br />

vendor.<br />

Risk decisions are supported by analyses and recommendations from the project team, but<br />

are ultimately made by the Project Manager in the same manner that all cost, schedule and performance<br />

impact decisions are made. If the scope of any change impacts Level 1 or 2 requirements,<br />

the management team, the advisory board, and Gemini are part of the decision process.<br />

The descope list provides the leverage for accepting reasonable risk and maintaining confidence<br />

that a meaningful instrument can be developed within the fixed budget even if many of the<br />

identified risks are actualized. The plan identifies functional or performance capabilities, which<br />

may be dropped at some later point of the project, allowing cost savings to be applied to the area<br />

where risks happened. It also describes where risks may be added (through dropping a test, or<br />

other activity with resulting cost avoidance) acceptably in order to cover unplanned costs in other<br />

areas. As with the risk list, the descope list will evolve through the instrument development and<br />

needs to be continuously assessed and updated.<br />

7.5 Reserves<br />

The total project reserves required is estimated at 20%; this 20% excludes the $8M allocated<br />

for the Subaru provided elements and does not factor in the Gemini-held contingency. The reserves<br />

are established by assessing risks associated with each WBS element (Management and<br />

Cost Volume, section 5.2). Higher reserves are allocated to areas that: 1) require more development<br />

effort and therefore have more uncertainty in meeting performance cost and schedule, 2)<br />

show risk of cost growth on procurements, 3) have a higher level of complexity in design or<br />

schedule coordination, and 4) have two or more identified significant risks at the project start.<br />

The reserves do not explicitly include an allocation for exchange rate uncertainty and instead a<br />

conservative exchange rate has been used to absorb rate fluctuations.<br />

Reserves above the partners’ contract-required 15% are held at JPL and managed at the project<br />

level to provide maximum flexibility in risk management. Allocation of reserves is a process<br />

that references the specific risk item and balances resources according to the summary of risks,<br />

schedule, and remaining resources. The project risks and reserves are reviewed and updated<br />

monthly with the project team and Gemini and quarterly with the advisory board. A clear assessment<br />

and justification for the release of reserves is developed with the subsystem leads to<br />

assess the impact across the instrument system. The final decision is made by the PM with concurrence<br />

from the PI. The advisory board will be notified of the potential for significant changes<br />

as they arise. A minimum level of reserves for each project phase is defined and managed to ensure<br />

sufficient funding is available through delivery. This is discussed further in the Management<br />

and Cost Volume.<br />

81

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!