Planning Committee <strong>Agenda</strong> Item 8<br />
13 April 2011 11/00126/F<br />
6.41 As the planning condition provides the option not to provide a CHP plant,<br />
<strong>and</strong> the development will still provide renewable energy that is in line with<br />
the South East Plan, this will need to be the subject of further detailed<br />
consideration.<br />
Contaminated L<strong>and</strong><br />
6.42 A desk study, site investigation report <strong>and</strong> remedial action plan for phase<br />
two of the Horley North East Sector were produced in November 2006. The<br />
site investigation report identified the presence of ground gases <strong>and</strong> material<br />
impacted by contamination in the Tanyard Farm area of the site. Details<br />
presented in the remediation action plan to address the contamination<br />
that was identified were vague <strong>and</strong> did not take into account the proposed<br />
layout of the site.<br />
6.43 In order to maintain control of works to address the contamination identified<br />
in the area of Tanyard Barn, it is necessary that future investigation <strong>and</strong>/or<br />
remediation works are agreed with the Local Planning Authority prior to<br />
such works being undertaken <strong>and</strong> development commencing in this area. A<br />
validation/closure report to record the works undertaken to ensure that the<br />
site was suitable for its proposed use will also be required prior to the<br />
development being occupied.<br />
CONDITIONS<br />
Pre-Commencement Conditions<br />
1. No development shall take place until a Construction Method Statement has<br />
been submitted to <strong>and</strong> approved in writing by the Local Planning Authority.<br />
Development shall be carried out only in accordance with the approved<br />
Construction Method Statement, which shall include details of:<br />
Highway Matters<br />
(a) Parking for vehicles of site personnel, operatives <strong>and</strong> visitors;<br />
(b) A programme of works (including measures for traffic management);<br />
(c) The provision of boundary hoarding in accordance with the details<br />
contained within the Construction Method Statement, Phase 1<br />
document prepared by Terry Ship on behalf of Barratt Wates <strong>and</strong> dated<br />
20 May 2008, Version 1;<br />
Flora <strong>and</strong> Fauna<br />
(d) Protection of existing fauna identified for retention, as detailed within<br />
the Environmental Statement;<br />
Environmental Health<br />
(e)<br />
Measures to prevent ground water contamination pollution; <strong>and</strong><br />
M:\BDS\DM\Ctreports 2010-11\Meeting 13- 13 April 2011\Agreed Reports\04.01778.RM13 - Horley NE Sector Phase 2.docx