Lee Tunnel, Contract No. <strong>6LYG</strong>/<strong>A1</strong><br />

PT – <strong>Particular</strong> <strong>Tunnelling</strong> <strong>Specification</strong> - PT200<br />

PT224.5<br />

e) During forward movement of the TBM, the guidance system shall provide as<br />

a minimum the following real-time data for the TBM, with reference to the<br />

designed tunnel alignment at the machine head:<br />

i) Station (chainage)<br />

ii) Horizontal/line displacement<br />

iii) Vertical/level/grade displacement<br />

iv) Left or right lead/yaw at axis level<br />

v) Overhand or look-up/pitch at axis level<br />

Main axis rotation<br />

This information shall be presented in numerical and graphical form, refreshed<br />

every 20 seconds or faster.<br />

PT224.6 The accuracy and the limits of each measurement shall be as stated in Table 1<br />

Accuracy and Limits of Position Measurements.<br />

Table 1 Accuracy and Limits of Position Measurements<br />

Data Accuracy (+/-) Limit (+/-)<br />

Station (chainage) (6mm) (12mm)<br />

Horizontal displacement (6mm) (6mm)<br />

Vertical displacement (6mm) (6mm)<br />

Left or right lead (3mm) (6mm)<br />

Overhang or look-up (3mm) (6mm)<br />

Main axis rotation (3mm) (12mm)<br />

PT224.7<br />

PT224.8<br />

PT224.9<br />

PT224.10<br />

PT224.11<br />

The data shall be presented on displays at the underground Machine Operators<br />

position and at the offices on surface of the Contractor and the Project Manager<br />

(three displays in all). Facilities to download data electronically (for further<br />

transmission) and for paper printout, independently of the current display, shall be<br />

provided at both offices.<br />

Data shall be recorded in a medium unaffected by primary power loss in a store<br />

of sufficient capacity to hold the entire tunnels production records.<br />

The guidance system shall, throughout the forward movement of the TBM,<br />

compute the correct curve which returns the TBM tangentially to the designed<br />

tunnel alignment and compute and display the necessary corrections to attitude<br />

to be applied during the course of the forward movement. This computed data<br />

may be used directly as input into the control mechanism of the TBM body and<br />

the excavation and between the tail skin and lining.<br />

The guidance system should also facilitate construction of the tunnel lining so that<br />

it follows, and does not bind onto, the TBM. The system shall provide data<br />

defining the plane of the circumferential joint of the leading edge of the tunnel<br />

lining with respect to Designed Tunnel Alignment and TBM axis.<br />

Procedural Aspects<br />

The operation of the guidance system shall be a specific feature of the<br />

Contractor’s Quality Assurance Plan. This should clearly address:<br />

a) Definition of responsibility and authority of personnel maintaining and<br />

operating the guidance system.<br />