Lee Tunnel, Contract No. <strong>6LYG</strong>/<strong>A1</strong><br />

PT – <strong>Particular</strong> <strong>Tunnelling</strong> <strong>Specification</strong> - PT200<br />

PT238.2<br />

PT238.3<br />

PT238.4<br />

PT238.5<br />

PT238.6<br />

PT238.7<br />

PT238.8<br />

• The Quality Management / Quality Assurance (QM/QC) for the tunnelling<br />

process, including its reporting system (Non-Conformance Reports and<br />

Remedial Work Reports, etc.),<br />

• The ring erection data,<br />

• Ground surface, ground settlements,<br />

• The alignment data,<br />

• Display of the geology along the alignment, and statistic evaluations.<br />

The data shall be transferred automatically, into the DAVARS.<br />

The DAVARS shall allow the Employer and his representatives to execute by<br />

themselves, visualisation in any display combination of sensors and data labels.<br />

Real time data input<br />

a) One set of all data generated by the TBM, the mucking systems, tunnel<br />

guidance system and, if applicable, automated surveillance systems, shall be<br />

read into the data base at least every ten seconds.<br />

b) This data shall be transferred directly by the equipment’s PLC and must not<br />

be handled through a secondary data system.<br />

c) Procedures, which are controlled and recorded in intervals longer then one<br />

hour, shall be introduced into the data base manually by the Contractor on<br />

the same day.<br />

Accessibility of DAVARS<br />

a) The data shall be stored into a project data base, accessible through Internet<br />

by the Employer and his authorised representatives at any time.<br />

b) The DAVARS shall be kept operational for the Employer from TBM<br />

installation in the launch position throughout the project until final acceptance<br />

and financial closure of the Project.<br />

c) The Employer will receive one electronic copy of the database at the end of<br />

the Project.<br />

Further Functions of DAVARS<br />

a) The DAVARS shall allow printing and emailing of the graphs and reports at<br />

any work place while being logged-in.<br />

b) The DAVARS shall allow for applying active triggers to arbitrary parameters<br />

and connecting the triggers with message functions. Passing the set trigger<br />

level shall initiate a notification by email to selected individuals.<br />

Real Time Data Management<br />

The Contractor shall provide Shift Records using semi- automatic Real Time Data<br />

Loggers software for on-line display and in hard copy to the Project Manager,<br />

detailing work performed except where otherwise allowed or accepted herein,<br />

and integrated with requirements specified elsewhere for erection of precast<br />

segments, cavity grouting, and permeation grouting including:<br />

a) Date, location, shift and beginning and ending face station. A manual check<br />

of the TBM face location shall be conducted on a weekly basis.<br />

b) List of personnel by name, classification, and function working that shift.<br />

c) List of the number and type of equipment, including amount of and reason for<br />

any idle or down time.<br />

d) List of all materials used in the work.<br />

For every TBM shove or stroke:<br />

Thames Water Utilities Limited August 2008<br />

Page 28 of 38