Lee Tunnel, Contract No. <strong>6LYG</strong>/<strong>A1</strong><br />

PT – <strong>Particular</strong> <strong>Tunnelling</strong> <strong>Specification</strong> - PT200<br />

assembly of the TBM in the Launch shaft, as well as for start-up and operation of<br />

the TBM for the first 1000mtrs of the tunnel drive. The technical representative<br />

shall certify in writing to the Project Manager that the TBM, as assembled, meets<br />

the Specified requirements.<br />

PT231<br />

PT231.1<br />

PT231.2<br />

PT232<br />

PT232.1<br />

PT232.2<br />

PT232.3<br />

PT233<br />

PT234<br />

QUALITY PLAN<br />

Within 4 weeks from award of Contract the Contractor shall submit a detailed<br />

Quality Plan based upon the Preliminary Quality Plan provided as a submittal<br />

under PT204.<br />

The Quality Plan shall be regularly updated to reflect any changes made to the<br />

procedures.<br />

PERSONNEL AND TRAINING<br />

The Contractor shall ensure that all key personnel who are responsible for<br />

driving, maintenance and controlling the TBM, including any specialist for the<br />

TBM computer systems, have received the necessary training in the duties that<br />

they are required to perform. Such training shall include emergency procedures.<br />

The Contractor shall provide and maintain a complete register of the names of<br />

persons, and their duties, responsible for the operation of the TBM, who have<br />

completed the appropriate training to an accepted standard.<br />

The Contractor shall provide a foreman fitter on site for the duration of the<br />

tunnelling works. A fitter and electrician shall be provided for every shift. The<br />

Contractor shall provide the Project Manager with copies of the curriculum vitae<br />

for all fitters and electricians.<br />

TUNNEL HEALTH AND SAFETY ASSURANCE<br />

As part of the Contractor’s Safety programme the Contractor shall produce a<br />

Tunnel Specific Safety Statement within 3 months of contract award detailing the<br />

precautions to be implemented to protect personnel working in the tunnel from<br />

the construction methodology risks associated with tunnelling at the designed<br />

gradients and long section. These shall include but not limited to:<br />

• Risk of runaway trains and derailments.<br />

• Tunnel inundations.<br />

• Control of water and standby provisions.<br />

• Temporary Tunnel Ventilation System.<br />

• Emergency evacuation of tunnel.<br />

• Fire precautions including the role of the appropriate fighting authority in the<br />

event of a tunnel fire. The procedure shall need to address all possible fire<br />

location and tunnel length scenarios.<br />

• Management of rail and pedestrian movements in the tunnel.<br />

REGULATIONS<br />

The design and manufacture of the TBM and back up systems shall comply with<br />

all relevant regulations and codes of practice including, but not limited to those<br />

described below. The Contractor shall ensure he always uses the latest published<br />

version of any standard that relates to safety. These shall include but are not<br />

limited to:<br />

• Section 6: Health and Safety at Work Act.<br />

• A Guide to working in Compressed Air 1996 guidance on oxygen<br />

decompression.<br />

Thames Water Utilities Limited August 2008<br />

Page 24 of 38