Lee Tunnel, Contract No. <strong>6LYG</strong>/<strong>A1</strong><br />

PT – <strong>Particular</strong> <strong>Tunnelling</strong> <strong>Specification</strong> - PT200<br />

PT245<br />

PT246<br />

PT246.1<br />

PT246.2<br />

PT246.3<br />

PT246.4<br />

PT247<br />

PT247.1<br />

PT247.2<br />

TBM LAUNCH FROM OVERFLOW SHAFT<br />

The TBM will be launched from the 25m ID Overflow Shaft at Beckton STW.<br />

From the Site Information and GBR, the launch of the TBM will be within the<br />

Greenwich Fault Zone of the chalk, the Employer views this as one of the highest<br />

risks to the success of this Project and the Contractor shall, within 28 days of the<br />

award of Contract, submit to the Project Manager a detailed Method Statement of<br />

his Means and Methods for the launch of the TBM, including ground treatment<br />

and temporary works proposals. A Risk Assessment shall also be provided.<br />

CONSTRUCTION TOLERANCES<br />

Bored Tunnel Tolerances<br />

a) Tunnel shall be constructed to the alignment as defined in the Works<br />

Information.<br />

b) Maximum tolerances allowed in respect of the departure of any point on the<br />

bored tunnel alignment from its designed centreline shall not exceed 50mm<br />

horizontally and 50mm vertically.<br />

d) No ponding anywhere in the tunnel shall be deeper than 25mm.<br />

e) The maximum and minimum measured diameter in any one ring shall be<br />

within 0.5% of the theoretical design diameter of the ring.<br />

f) The maximum lipping between the edges of the adjacent segments shall not<br />

exceed 5mm.<br />

Inner Lining Tolerances<br />

a) At no point shall the lining thickness be less than that recommended by the<br />

designer.<br />

b) As stated in PT246.1 the maximum departure of any point on the inner lining<br />

shall not exceed 50mm from its designed position.<br />

c) No ponding anywhere in the tunnel shall be deeper than 25mm<br />

d) The internal diameter of the inner lining measured at any point around the<br />

circumference shall depart no more than 10mm from the designed diameter.<br />

e) If cast in sections there shall be no lipping between the panel joints.<br />

Groundwater Ingress Primary Lining<br />

a) The infiltration volume of water for the total length of tunnel shall not exceed<br />

0.1 litre per hour per linear metre of nominal bore.<br />

b) Sealing of leaks in the segmental lined tunnel shall be carried out prior to the<br />

secondary lining installation<br />

Groundwater Ingress Inner Lining<br />

There shall be no visible damp patches or running water present on the finished<br />

surface of the lining.<br />

AS-BUILT TUNNEL SURVEY<br />

On completion of the tunnel construction the Contractor shall carry out an As-Built<br />

Tunnel Survey in the bored tunnel. The accuracy of the survey shall be to ±20mm<br />

for vertical and horizontal alignment.<br />

The As-Built Tunnel Survey shall be completed as soon as practical following the<br />

completion of the tunnel, the As- Built Survey data is to be finalized and<br />

submitted to the Project Manager prior to the final acceptance of the tunnel.<br />

Thames Water Utilities Limited August 2008<br />

Page 36 of 38