(c) Examine, assess the equivalence of and approve any alternative<br />

equipment/materials proposed by the Contractor, or sub-contractors. Ensure this<br />

process is undertaken in strict compliance with the „Public Contract Regulations‟.<br />

(d) Coordinate and manage the inspection, supervision and approval of the works<br />

between the Clerk of Works/Supervisor (NEC) and the various disciplines within the<br />

design team.<br />

(e) Organise lighting trials for the benefit of DCC/NITB/BHP.<br />

(f) Ensure compliance of all parties with CDM regulations.<br />

(g) Coordinate and manage regular site progress and technical meetings between client<br />

team, design team, contractor and sub-contractors and any other third parties i.e.<br />

adjacent land owners, service authorities, etc.<br />

(h) Undertake all contract administration duties and measure/certify the value of the<br />

works completed satisfactorily on a monthly basis.<br />

(i) Coordinate, manage and witness the testing and commissioning of the works<br />

between the Clerk of Works/supervisor and the various disciplines within the design<br />

team.<br />

(j) Coordinate and management training and demonstration of the works to DCC/BHP<br />

and any other interested parties.<br />

(k) Undertake thorough inspection of „completed‟ works and compile any defect lists.<br />

Oversee timely completion/rectification of any defects.<br />

(l) On completion of the works receive, inspect and approve a full set of „as built‟ record<br />

information of the works including drawings, operating instructions and maintenance<br />

manuals. Compile a separate document for each building/monument/structure.<br />

(m) Coordinate and management a post completion contract review procedure, including<br />

KPI‟s.<br />