• The installation contractor is responsible for accepting delivery and storage of material<br />

furnished by other contractor(s), in accordance with the requirements of the contract. The<br />

installation contractor must furnish and install all ancillary components to provide complete<br />

installation for proper operation of equipment and material.<br />

Question (9): Who furnishes and installs smart boards?<br />

Answer (9):<br />

Smart boards shall be furnished and installed by the Electrical Contractor. See Specialty<br />

Equipment Schedule on Drawings A>401.00, A>402.00, A>403.00, A>404.00, and A>407.00.<br />

Question (10): Spec Section 013529 Note 11 – Does GC provide watchmen service?<br />

Answer (10): The General Contractor shall provide security services for the <strong>STV</strong> Construction Field Office<br />

and Equipment. The General Contractor is also responsible for the security of the work site and<br />

to provide suitable site protection to prevent unauthorized entry onto the site, until final<br />

acceptance by CUNY, in accordance with contract requirements.<br />

Question (11): Spec Section 015100>2E – Where can we place temp toilets?<br />

Answer (11): Queens College will provide an area on campus outside the Science Building for the General<br />

Contractor to locate temporary toilets.<br />

Question (12): Spec Sect 05100>3H – Is temp fence required?<br />

Answer (12): Temporary fencing is not required.<br />

Question (13): Spec Sect 011116>11 2.2 a>1 calls for temp barricades. Please provide locations where these<br />

barricades are to be constructed.<br />

Answer (13): Temporary construction barricades are required in the corridors adjacent to the entrances of the<br />

laboratories within the scope of work for this project. General Contractor shall comply with<br />

Section 011116 of the General Requirements for design of the temporary construction barricade.<br />

Question (14): Spec Sect 011116>9 1.9 – Note 9 calls for masonite protection of floors. Can this protection be<br />

left in place or must it be picked up and reinstalled on daily basis?<br />

Answer (14): The General Contractor is permitted to leave protection in place as long as it is maintained on a<br />

daily basis, presents no tripping hazard, and does not obstruct doors or create any type of access<br />

issues, in accordance with the contract General Requirements.<br />

<strong>STV</strong> Construction, <strong>Inc</strong>.<br />

Addendum No. 1 (09>20>12) Page 4 of 6<br />

CITYW>CUCF>01>09>04>GC/MECH/EL/PL