13.07.2015 Views

Warrawee Substation - Submissions Report - Transport for NSW ...

Warrawee Substation - Submissions Report - Transport for NSW ...

Warrawee Substation - Submissions Report - Transport for NSW ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

All written submissions received during the extended public exhibition period, including latesubmissions, regarding the proposed <strong>Substation</strong> will receive an individual response to theirsubmission. The issues identified in all submissions will also be collated into a submissionsreport that will be made publically available at:http://www.railcorp.info/community/warraweesubstation<strong>Submissions</strong> received will be considered by RailCorp when deciding whether the project in itspresent <strong>for</strong>m should be approved in accordance with the provisions of Part 5 of theEnvironmental Planning and Assessment Act 1979, to allow construction to commence.If the project is approved, regular construction updates would be provided and wherenecessary, targeted door knocking would occur. Ongoing community engagement wouldensure community concerns and needs are addressed. In addition, the Project Info Line 0477335 236 would remain operational to address any enquiries or complaints.3.3.6 Why was the project notification letter only delivered toBrentwood Ave residents and not the broader community?Issue Addressed: Consultation Process, Project Approval ProcessAddressing <strong>Submissions</strong>: 3, 5, 7, 8, 11, 12, 13, 14, 15, 16, 22, 23, 24, 27, 33, 34, 36, 37, 38RailCorp’s standard area <strong>for</strong> community consultation around a proposed site is 250 metres.As requested by the local community in <strong>Warrawee</strong>, RailCorp extended the consultation areato approximately 500 metres from the proposed site and also extended the time period <strong>for</strong>residents to provide their submissions to the REF.3.3.7 How does RailCorp obtain approval to construct a substation?Issues Addressed: Project Approval ProcessAddressing <strong>Submissions</strong>: 3, 5, 7, 8, 11, 12, 13, 14, 15, 16, 22, 23, 24, 27, 33, 34, 36, 37, 38RailCorp follows the process outlined below:Stage one: 21-day statutory notification period (until 23 May 2012 and then extended until 7June 2012).Review of Environmental Factors made available <strong>for</strong> review and comment under the stateEnvironmental Planning Policy (Infrastructure) 2007. Nearby residents and other stakeholdersnotified by letter and doorknocking.Stage two: RailCorp assesses submissions. <strong>Submissions</strong> report prepared to address andrespond to submissions. This report is submitted with the REF <strong>for</strong> determination.Stage three: RailCorp determination. Determination of final REF and conditions of approvalissued.Stage four: Commencement of construction. Construction will begin, with nearby residentsreceiving additional notification at least five working days be<strong>for</strong>e construction begins.3.3.8 Will residents be compensated <strong>for</strong> the inconvenience caused bythe construction of the substation over the proposed three yearperiod?Issues Addressed: Visuals Impact and CompensationAddressing <strong>Submissions</strong>: 1, 6, 7, 16, 19, 20, 24, 26, 27, 30, 32 and 34Page 18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!