eports on the faulty components’ issue”. 72 In the following, ninth semi‐annual IAB report, basedon meetings held in March 2014, it is stated that “to date there has not yet been a case of CFSI[Counterfeit, Fraudulent and Suspect Items] concerning equipment of materials supplied orinstalled at the BNPP [Barakah Nuclear Power Plant]”. 73Construction started in November 2013 at Belarus’s first nuclear reactor at the Ostrovetspower plant, also called Belarusian‐1. Construction of a second 1200 MWe AES‐2006 reactorstarted in June 2014.In November 2011, the two governments agreed that Russia would lend up to US$10 billion for25 years to finance 90 percent of the contract between Atomstroyexport and the BelarusDirectorate for Nuclear Power Plant Construction. In February 2012, Russian state‐owned bankVneshekonom‐bank (VEB), and the Belarusian commercial bank Belvneshekonombank signed anagreement to implement the Russian export credit facility. In July 2012, the contract was signedfor the construction of the two reactors for an estimated cost of US$10 billion, including US$3billion for new infrastructure to accommodate the remoteness of Ostrovets in northern Belarus. 74The project assumes the supply of all fuel and repatriation of spent fuel for the life of the plant.The fuel is to be reprocessed and the separated wastes returned to Belarus. In August 2011, theMinistry of Natural Resources and Environmental Protection of Belarus stated that the first unitwould be commissioned in 2016 and the second one in 2018. 75 However, these dates were revisedand when construction was started it was stated that the reactors will not be completed until2018 and 2020. 76 In March 2015, Atomstroyexport admitted the plant would cost 1,433.7 billionRubles compared to the forecast from 2014 of 840 billion Rubles. At exchange rates of March2015, when the Ruble was valued at about half the level of 2014, this equates to an original costestimate of $US13 billion, increasing by 71 percent to US$22.9 billion.The project is the focus of international opposition and criticism, with formal complaints from theLithuanian government 77 and Belarus has been found to be in non‐compliance with some of itsobligations concerning the construction of the Ostrovets NPP (Nuclear Power Plants), accordingto the meeting of the Parties of the Espoo Convention. 78 The extent of international opposition tothe project was reported in Nuclear Intelligence Weekly (NIW), where it said that during theIAEA’s general conference, “a slick presentation from the major government players in the72 Ibidem.73 IAB, “Ninth Semi‐Annual report 2014”, International Advisory Board for the UAE nuclear program,undated, see http://www.uaeiab.ae/download.php?f=publications/IAB_Annual_%20Report_2014_EN.pdf,accessed 7 June 2015.74 Nuclear Intelligence Weekly (NIW), “Belarus, Aided by Russia and Broke, Europe’s Last DictatorshipProceeds With NPP”, 28 September 2012.75 V.V. Kulik, Deputy Minister, Ministry of Natural Resources and Environmental Protection of the Republic ofBelarus, Letter to the European Commission, dated 9 August 2011.76 WNN, “Ostrovets plant meets construction safety rules”, 7 November 2014.77 Bloomberg, “Lithuania Urges Belarus to Halt Nuclear Project on Safety Issues”, 20 August 2013, seehttp://www.bloomberg.com/news/2013‐08‐20/lithuania‐urges‐belarus‐to‐halt‐nuclear‐project‐on‐safetyissues.html,accessed 10 June 2014.78 United Nations Economic Commission for Europe (UNECE), “Parties to UNECE treaties adopt declarationon applying environmental assessment procedures to nuclear energy issues”, Press Release, 13 June 2014.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 45
Belarussian nuclear program did little to impress international experts and diplomats.” 79 Thetrade journal also reported domestic criticism of the project on the grounds of the signing ofcontracts with a Russian company of poor reputation and that no detailed economic justificationof the plant had been presented. The Government had projected electricity costs from the plant inthe order of $US45/MWh, which is significantly lower than similar projects being proposed inother countries, for example in Jordan.In Turkey, two projects are being developed, but rather than proceeding with a single builderand design, the Government has decided to undertake at least two different reactor designs and atleast two different sets of contractors.The first project, on the southern coast, is at Akkuyu, which is to be built under a Build‐Own‐Operate‐ (BOO) model by Rosatom of Russia. An agreement was signed in May 2010 for fourVVER1200 reactors, with construction originally expected to start in 2015, but now delayed untilat least 2016, and to cost US$20–25 billion for 4.8 GW. At the heart of the project is a 15‐year‐Power Purchase Agreement (PPA), which includes 70 percent of the electricity produced fromunits 1 and 2 and 30 percent of units 3 and 4. Therefore 50 percent of the total power from thestation will be sold at a guaranteed price for the first 15 years, with the rest to be sold on themarket, where the average wholesale electricity price for 2010 was US$93.8/MWh. The electricityprice within the PPA (excluding value added tax) is reported to be U$123.5/MWh, with apossibility to increase the price up to US$153.3/MWh to ensure the payback of the project. 80Furthermore, the fixed price of the PPA is above the feed‐in tariffs being offered for renewables,as the prices for 10 years for hydro and wind are US$73/MWh, geothermal US$105/MWh, andsolar US$103 /MWh. 81The CEO of Akkuyu JSC (the project company set up by Russia's Rosatom) Alexander Superfin,said in October 2013 that the project was going to be operational by mid‐2020, a delay of about18 months from an earlier planned start‐up date. However, further delays are likely as there havebeen problems with the Environmental Impact Assessment (EIA), which when submitted in July2013 was rejected by the Ministry of Environment. However, when it was eventually approved inDecember 2014, it was said that the commissioning of the first unit was likely to be in 2021. 82 In79 NIW, “Belarus—A chilled Reception in Vienna”, 27 September 2014.80 Marco Cometto, “Financing the Akkuyu NPP in Turkey”, OECD/NEA, Nuclear Development Division, aspresented at OECD/NEA Workshop on Electricity price and Nuclear New Build, 19 September 2013, seehttp://www.oecd‐nea.org/ndd/workshops/wpne/presentations/docs/4_1_Cometto_Akkuyu.pdf, accessed14 July 2014.81 Chadborne and Parke, “Turkey Moves to Boost Renewable Energy; new feed‐in tariffs and other incentives forrenewable energy”, January 2011, see http://www.chadbourne.com/Turkey_Renewable_Energy_projectfinance/,accessed 14 July 2014.82 WNN, “Akkuyu project EIA gets ministry approval”, 1 December 2014.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 46
- Page 2: This page is intentionally left bla
- Page 9: Figure 32: Age Pyramid of the 131 N
- Page 12 and 13: new company called Uniper. And in A
- Page 14 and 15: Reactor Status and Nuclear Programs
- Page 16 and 17: in 2015. Historic analysis shows th
- Page 18 and 19: Olympic swimming pools. A groundwat
- Page 20 and 21: "For all intents and purposes, AREV
- Page 22 and 23: On 8 June 2015, the U.S. utility in
- Page 24 and 25: The world’s nuclear statistics re
- Page 26 and 27: According to the latest assessment
- Page 28 and 29: first in which there was zero nucle
- Page 30 and 31: definitive closure of the Indian re
- Page 32 and 33: Table 1: Nuclear Reactors “Under
- Page 34 and 35: and ‐4 in Ukraine are approaching
- Page 36 and 37: Figure 9: Construction Starts in th
- Page 38 and 39: ecent design and compliant with sig
- Page 40 and 41: clear that the 3/11 events had an i
- Page 42 and 43: Figure 15: The 40‐Year Lifetime P
- Page 44 and 45: Bangladesh, Belarus, Turkey, UAE, a
- Page 48 and 49: January 2015, both the Chamber of T
- Page 50 and 51: conditions of financing and partici
- Page 52 and 53: of the contract, with Rosatom cover
- Page 54 and 55: start construction in the next 2-3
- Page 56 and 57: In the late 1990s, the nuclear indu
- Page 58 and 59: AES‐2006 have received orders, wh
- Page 60 and 61: shortage of skilled labor; quality
- Page 62 and 63: use of passive features in the EPR
- Page 64 and 65: there have been a number of other i
- Page 66 and 67: standardize. Without standardizatio
- Page 68 and 69: Leningrad‐2‐1 Russia AES‐2006
- Page 70 and 71: ut noted that these “had varying
- Page 72 and 73: (IRIS) design. The design started i
- Page 74 and 75: or early 2013. 219 In 2011, it was
- Page 76 and 77: national energy bureau around two w
- Page 78 and 79: scale they would manage to lower th
- Page 80 and 81: The top of the reactor building of
- Page 82 and 83: TEPCO and the Government are planni
- Page 84 and 85: out that TEPCO’s lax management o
- Page 86 and 87: physical condition or suicide (“e
- Page 88 and 89: In March 2015, Fukushima Prefecture
- Page 90 and 91: “Rising long‐term natural gas p
- Page 92 and 93: projects came in at an average of U
- Page 94 and 95: Figure 20: Wind, Solar and Nuclear,
- Page 96 and 97:
to rapidly accelerate the use of lo
- Page 98 and 99:
• In Germany, renewables provided
- Page 100 and 101:
target is undoubtedly ambitious, bu
- Page 102 and 103:
Annex 1: Overview by Region and Cou
- Page 104 and 105:
U.S. that have “shown interest in
- Page 106 and 107:
The construction of Angra‐3 was s
- Page 108 and 109:
project boosted the nameplate capac
- Page 110 and 111:
Shuttering old, uneconomic reactors
- Page 112 and 113:
In the case of Vogtle, a report for
- Page 114 and 115:
limit their competitiveness to meet
- Page 116 and 117:
generation projects in oversupplied
- Page 118 and 119:
identified and solved will we allow
- Page 120 and 121:
commercial operation only on 31 Dec
- Page 122 and 123:
TEPCO that its staff had deliberate
- Page 124 and 125:
produce plutonium for use in MOX fu
- Page 126 and 127:
Power's Takahama‐3 and ‐4, with
- Page 128 and 129:
Kansai Electric, along with Kyushu
- Page 130 and 131:
permanent closure of five reactors
- Page 132 and 133:
contractor and China Nuclear Indust
- Page 134 and 135:
in May 2013, when the NSSC, followi
- Page 136 and 137:
The political consequences of the m
- Page 138 and 139:
The European Union 28 member states
- Page 140 and 141:
In the absence of any successful ne
- Page 142 and 143:
of the serious concerns by a range
- Page 144 and 145:
negative outlook, “owing to conti
- Page 146 and 147:
The average age of France’s power
- Page 148 and 149:
EDF shares lost up to 85 percent of
- Page 150 and 151:
power output is expected to rise si
- Page 152 and 153:
low 639 , and coal‐fired generati
- Page 154 and 155:
under construction. It was therefor
- Page 156 and 157:
utilize the fuel that it obtained b
- Page 158 and 159:
opinion at any of the sites propose
- Page 160 and 161:
In Bulgaria, nuclear power provided
- Page 162 and 163:
criteria defined in the tender”.
- Page 164 and 165:
signed a binding agreement that mad
- Page 166 and 167:
let the reactor operate until 2026.
- Page 168 and 169:
time of ordering, the reactors were
- Page 170 and 171:
intergovernmental agreement to comp
- Page 172 and 173:
Takahama‐1 (PWR) 826 1974 - 40 10
- Page 174 and 175:
IAEA have chosen to limit the LTS c
- Page 176 and 177:
Note: SFP: Spent Fuel Pool, RPV: Re
- Page 178 and 179:
Table 10: Definition of Credit Rati
- Page 180 and 181:
Monticello 3/71 3/05 11/06Palisades
- Page 182 and 183:
(as of 10 June 2015) 764Table 12: C
- Page 184 and 185:
2. Chinese Nuclear Power Plants Und
- Page 186 and 187:
2006-08, he carried out research at
- Page 188 and 189:
CGN or CGNPC - Chinese General Nucl
- Page 190 and 191:
INS - Indian Nuclear SocietyINSAC -
- Page 192 and 193:
NSSC - Nuclear Safety and Security
- Page 194 and 195:
UNSCEAR - United Nations Scientific
- Page 196 and 197:
Romania 2 1 300 14 18. 5% (‐) 8%
- Page 198 and 199:
Shandong Shidaowan 200 01/12/12 2/2
- Page 200 and 201:
USA 5 5 633Virgil C. Summer‐2 111
- Page 202:
25 Delayed numerous times. Latest I