there have been a number of other issues such as design issues (squib valves), poordocumentation, and quality issues. Like Taishan, there are increasing concerns aboutcommissioning tests and acceptance criteria.Westinghouse claims the problems with the reactor coolant pumps emerged early enough forthem to be avoided for the U.S. orders, which will use a different manufacturing process for theimpellers. For the U.S. plants, there has been a large number of problems in the factories of themodule suppliers, especially Chicago Bridge & Iron (CB&I). From the beginning of 2013 to 1 May2015, the pumps’ vendor CB&I had had to inform the NRC of 65 failures “to comply with theAtomic Energy Act (AEA) of 1954, as amended, or other NRC regulations.” 169A senior executive with CB&I said: “The suppliers really struggled understanding the exact natureof what we wanted, how to stand up [nuclear quality assurance] programs. Getting suppliers upthe learning curve on what was expected in terms of quality and how that process had to workwas quite difficult”. 170The development of the AES‐2006 is more complex than that of EPR or AP1000, partly because,while Rosatom is the umbrella organization for all the major Russian nuclear companies, thereappears to be considerable overlap between different subsidiaries. There are two major nucleardesign companies, Moscow Atomenergoproekt and Saint‐Petersburg Atomenergoproekt, whichgenerally have their own distinctive versions of the same basic design, including AES‐2006. Athird design company, Nizhniy Novgorod Atomenergoproekt, exists but does not seem to be asimportant as the other two. Rosatom presents the successive versions of the VVER (the Russianversion of the PWR) as a smooth evolution with Rosatom emphasizing the additional safetyfeatures that each successive model included. 171 There were two early post‐Chernobyl designs,AES‐91/V‐428 (Saint‐Petersburg Atomenergoproekt) exported to China and AES‐92/V‐412(Moscow Atomenergoproekt) exported to India. The reactor was essentially the same as itspredecessor, VVER‐1000/V‐320), but with added safety systems including a core‐catcher andsome passive safety systems. Both models are still being offered, for example to markets likeJordan where the extra output of the AES‐2006 would be difficult to accommodate.The AES‐2006 comes in two versions, V‐392M designed by Moscow Atomenergoproekt with twounits under construction at Novovoronezh, and V‐491, designed by Saint‐PetersburgAtomenergoproekt and under construction at the Leningrad, Belarus, and the Baltic sites,although work at the Baltic site was suspended in 2013 and appears unlikely to restart. It is notclear which versions would be exported to the numerous export orders Rosatom claims but onwhich construction has not started, such as Turkey and Vietnam. There are differences betweenthe two variants in terms of their passive safety systems.Work on a successor design, VVER‐TOI/V‐520 developed by Moscow Atomenergoproekt andbased on V‐392M, quickly started and by 2010, it was said the new design would be available169 U.S.NRC, “Part 21 Reports”, Updated 22 May 2015, see http://www.nrc.gov/reading‐rm/doccollections/event‐status/part21/,accessed 22 May 2015.170 NW, “US experiences nuclear construction challenges, progress: industry”, 29 August 2013.171 Rosatom, “The VVER today”, Updated 11 March 2015, seehttp://www.rosatom.ru/en/resources/b6724a80447c36958cfface920d36ab1/brochure_the_veer_today.pdf,accessed 11 March 2015.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 63
from 2012, although by 2015 no orders had been placed. VVER‐TOI was expected to be 20percent cheaper and could be built in 40 months.First concrete was poured for the reactors sited in Russia from 2008–10 and these reactors arewhere substantive experience exists. The major reported incident was the collapse of the steelstructures for a containment build at the Leningrad site in 2011. It was only in 2014 that firstreports of delays emerged and by 2015, all four reactors were 3–4 years late. However, a January2015 report from Russia’s Audit Chamber seemed to put the blame squarely on shortage offunds. 172 Whether there are other construction issues is difficult to tell. Two reactors using anolder design at the Rostov site were ordered at about the same time as the AES‐2006s; one ofthese was completed on time and the other appears close to schedule. It may be that this indicatesmore deep‐seated issues at Novovoronezh and Leningrad than just shortage of capital.The record of AES‐2006 seems somewhat better than that of EPR and AP1000, but the lack ofdetailed information on the AES‐2006 projects and the lack of transparency of the regulatorysystem means it is difficult to draw strong conclusions on the buildability of the AES‐2006compared to AP1000 and EPR.In terms of delays, the record of AP1000 and EPR appears comparably bad. The delays at theChinese AP1000 and EPR sites are similar to each other, and the delays at the U.S. AP1000 sitesare similar to those incurred at a comparable stage for EPR. Both designs have suffered a seriousdesign issue that has delayed construction. The instrumentation & control system for EPR causeddelays because of problems persuading the regulators of its adequacy. The reactor coolant pumpissue was somewhat different, with the problem being that the pump simply did not meet thedesign standard.However, the pattern of construction problems seems somewhat different. For EPR, there was asuccession of quality problems with sitework at both European sites, while the AP1000 sufferedserious quality issues at the module suppliers’ facilities, especially those of CB&I.The promise that Generation III+ designs would be simpler and therefore easier to build appearsnot to have been fulfilled. Real costs have increased significantly compared to their predecessorssuggesting the attempt to reduce complexity was not a success. The attempt to reduce siteworkby shifting the workload to factories through modularized design also does not seem to have hadthe desired effect, and seems to simply have shifted the quality issues from site to modulefactories.1. Standardization has not happened, and all three designs have seen significant andcontinuing design changes. The reality may be that nuclear technology is simply notmature enough to standardize yet and there is still a continuing flow of design changesdriven by experience of operating plants and technical change that it would be foolish toignore. The rate of ordering may also be too low for standardization to be feasible. Ifvendors are receiving only a handful of orders per decade, it seems to make little sense to172 NIW, “Auditor Report Illuminates Rosatom’s Financial Challenges”, 23 January 2015.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 64
- Page 2:
This page is intentionally left bla
- Page 9:
Figure 32: Age Pyramid of the 131 N
- Page 12 and 13:
new company called Uniper. And in A
- Page 14 and 15: Reactor Status and Nuclear Programs
- Page 16 and 17: in 2015. Historic analysis shows th
- Page 18 and 19: Olympic swimming pools. A groundwat
- Page 20 and 21: "For all intents and purposes, AREV
- Page 22 and 23: On 8 June 2015, the U.S. utility in
- Page 24 and 25: The world’s nuclear statistics re
- Page 26 and 27: According to the latest assessment
- Page 28 and 29: first in which there was zero nucle
- Page 30 and 31: definitive closure of the Indian re
- Page 32 and 33: Table 1: Nuclear Reactors “Under
- Page 34 and 35: and ‐4 in Ukraine are approaching
- Page 36 and 37: Figure 9: Construction Starts in th
- Page 38 and 39: ecent design and compliant with sig
- Page 40 and 41: clear that the 3/11 events had an i
- Page 42 and 43: Figure 15: The 40‐Year Lifetime P
- Page 44 and 45: Bangladesh, Belarus, Turkey, UAE, a
- Page 46 and 47: eports on the faulty components’
- Page 48 and 49: January 2015, both the Chamber of T
- Page 50 and 51: conditions of financing and partici
- Page 52 and 53: of the contract, with Rosatom cover
- Page 54 and 55: start construction in the next 2-3
- Page 56 and 57: In the late 1990s, the nuclear indu
- Page 58 and 59: AES‐2006 have received orders, wh
- Page 60 and 61: shortage of skilled labor; quality
- Page 62 and 63: use of passive features in the EPR
- Page 66 and 67: standardize. Without standardizatio
- Page 68 and 69: Leningrad‐2‐1 Russia AES‐2006
- Page 70 and 71: ut noted that these “had varying
- Page 72 and 73: (IRIS) design. The design started i
- Page 74 and 75: or early 2013. 219 In 2011, it was
- Page 76 and 77: national energy bureau around two w
- Page 78 and 79: scale they would manage to lower th
- Page 80 and 81: The top of the reactor building of
- Page 82 and 83: TEPCO and the Government are planni
- Page 84 and 85: out that TEPCO’s lax management o
- Page 86 and 87: physical condition or suicide (“e
- Page 88 and 89: In March 2015, Fukushima Prefecture
- Page 90 and 91: “Rising long‐term natural gas p
- Page 92 and 93: projects came in at an average of U
- Page 94 and 95: Figure 20: Wind, Solar and Nuclear,
- Page 96 and 97: to rapidly accelerate the use of lo
- Page 98 and 99: • In Germany, renewables provided
- Page 100 and 101: target is undoubtedly ambitious, bu
- Page 102 and 103: Annex 1: Overview by Region and Cou
- Page 104 and 105: U.S. that have “shown interest in
- Page 106 and 107: The construction of Angra‐3 was s
- Page 108 and 109: project boosted the nameplate capac
- Page 110 and 111: Shuttering old, uneconomic reactors
- Page 112 and 113: In the case of Vogtle, a report for
- Page 114 and 115:
limit their competitiveness to meet
- Page 116 and 117:
generation projects in oversupplied
- Page 118 and 119:
identified and solved will we allow
- Page 120 and 121:
commercial operation only on 31 Dec
- Page 122 and 123:
TEPCO that its staff had deliberate
- Page 124 and 125:
produce plutonium for use in MOX fu
- Page 126 and 127:
Power's Takahama‐3 and ‐4, with
- Page 128 and 129:
Kansai Electric, along with Kyushu
- Page 130 and 131:
permanent closure of five reactors
- Page 132 and 133:
contractor and China Nuclear Indust
- Page 134 and 135:
in May 2013, when the NSSC, followi
- Page 136 and 137:
The political consequences of the m
- Page 138 and 139:
The European Union 28 member states
- Page 140 and 141:
In the absence of any successful ne
- Page 142 and 143:
of the serious concerns by a range
- Page 144 and 145:
negative outlook, “owing to conti
- Page 146 and 147:
The average age of France’s power
- Page 148 and 149:
EDF shares lost up to 85 percent of
- Page 150 and 151:
power output is expected to rise si
- Page 152 and 153:
low 639 , and coal‐fired generati
- Page 154 and 155:
under construction. It was therefor
- Page 156 and 157:
utilize the fuel that it obtained b
- Page 158 and 159:
opinion at any of the sites propose
- Page 160 and 161:
In Bulgaria, nuclear power provided
- Page 162 and 163:
criteria defined in the tender”.
- Page 164 and 165:
signed a binding agreement that mad
- Page 166 and 167:
let the reactor operate until 2026.
- Page 168 and 169:
time of ordering, the reactors were
- Page 170 and 171:
intergovernmental agreement to comp
- Page 172 and 173:
Takahama‐1 (PWR) 826 1974 - 40 10
- Page 174 and 175:
IAEA have chosen to limit the LTS c
- Page 176 and 177:
Note: SFP: Spent Fuel Pool, RPV: Re
- Page 178 and 179:
Table 10: Definition of Credit Rati
- Page 180 and 181:
Monticello 3/71 3/05 11/06Palisades
- Page 182 and 183:
(as of 10 June 2015) 764Table 12: C
- Page 184 and 185:
2. Chinese Nuclear Power Plants Und
- Page 186 and 187:
2006-08, he carried out research at
- Page 188 and 189:
CGN or CGNPC - Chinese General Nucl
- Page 190 and 191:
INS - Indian Nuclear SocietyINSAC -
- Page 192 and 193:
NSSC - Nuclear Safety and Security
- Page 194 and 195:
UNSCEAR - United Nations Scientific
- Page 196 and 197:
Romania 2 1 300 14 18. 5% (‐) 8%
- Page 198 and 199:
Shandong Shidaowan 200 01/12/12 2/2
- Page 200 and 201:
USA 5 5 633Virgil C. Summer‐2 111
- Page 202:
25 Delayed numerous times. Latest I