conditions of financing and participation improved in cooperation with partners”. 99 In April 2014,the Prime Minster said that the project might proceed but that it was dependent on the answersto 80 questions submitted to Hitachi, which included questions on the costs of the project, theprice of electricity and the capabilities of synchronizing with the Western electricity grid. TheEnergy Minister, Jaroslav Neverovich, said there is a good chance the projects will proceed. 100 InJuly 2014 the Lithuania Energy Ministry and Hitachi signed an agreement to set up a joint venturefor the construction of the Visaginas nuclear power plant. However, as of June 2015, furtheragreements with other partners, namely Estonia and Latvia, had yet to be signed. 101In November 2011, the Bangladesh Government’s press information department said thatit would sign a deal with the Russian Government for two 1000 MW units to be built by 2018 at acost of US$2 billion. 102 Since then, while it is said negotiations have been ongoing, the start‐update was postponed, and the price has risen. In January 2013, Deputy Finance Minister of RussiaSergey Storchak and Economic Relations Division (ERD) Secretary of Bangladesh Abul KalamAzad signed the agreement on the Extension of State Export Credit for financing the preparatorystage work for the nuclear power plant at Rooppur (or Ruppur). 103 The deal was only forUS$500 million 104 and will only cover the site preparatory work. 105 In October 2013, a ceremonywas held for the formal start of the preparatory stage, 106 with formal construction then expectedto begin in 2015. At the time of the ceremony, the cost of construction was revised upwards and itwas suggested that each unit would cost US$1.5–2 billion. 107 These cost estimates tripled in April2014, when a senior official at the Ministry of Science and Technology was quoted as suggestingthe price was more likely to be US$6 billion. 108 In Russia, it is expected that the total cost of theproject is more likely to be around US$10 billion 109 , the cost of similar deals in Belarus andHungary. However, falls in the value of the Ruble are likely to affect the overall cost of the project.It is expected that Bangladesh will be responsible for 10 percent of the project with the rest of thefinancing in the form of a loan from Russia. In June 2014, the Cabinet Committee on Government99 Ministry of Energy of Lithuania, “Lithuanian Parliamentary Parties Reached an Agreement Regarding theKey Strategic Energy Projects”, 31 March 2014.100 Baltic Course, “Lithuania waiting for Hitachi’s answers to nearly 80 questions concerning NPP”, 2 April 2014.101 The Lithuanian Tribune, “Lithuanian energy minister expects new N‐plant talks to speed up after Estoniaforms new government”, 12 March 2015, seehttp://en.delfi.lt/nordic‐baltic/lithuanian‐energy‐minister‐expects‐new‐n‐plant‐talks‐to‐speed‐up‐afterestonia‐forms‐new‐government.d?id=67412324#ixzz3VIs6GcfQ,accessed 24 March 2015.102 Bloomberg, “Bangladesh to Sign Deal With Russia to Build Nuclear Power Plant”, 2 November 2011.103 Energy Bangla, “Bangladesh, Russia sign nuclear power pact”, 17 January 2013.104 All dollar (equivalent) amounts are expressed in U.S. dollars unless indicated otherwise. However, theyear’s dollars are not always clear in the original references.105 The Star, “Russia to lend $1.5B to Bangladesh to build nuclear power station, buy arms”, 15 January 2013.106 BBC, “Bangladesh nuclear power plant work begins”, 2 October 2013.107 Bangladesh Awami League, “PM Sheikh Hasina inaugurates Rooppur Power Plant”, seehttp://www.albd.org/index.php/en/updates/news/281‐pm‐sheikh‐hasina‐inaugurates‐rooppur‐power‐plant,accessed 25 March 2015.108 The Independent (of Bangladesh), “Roopur N‐plant cost to double”, 7 April 2014, seehttp://www.theindependentbd.com/index.php?option=com_content&view=article&id=210774:roopur‐nplant‐cost‐to‐double&catid=129:frontpage&Itemid=121,accessed 25 March 2015.109 Moscow Times, “Rosatom to Build Bangladesh's First Nuclear Power Plant”, 3 October 2013.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 49
Purchase approved a US$190 million procurement contract with Atomstoyexport for thepreconstruction work, with the start of actual construction expected for 2016. 110On 4 May 2015, the Government approved a draft of “The Nuclear Power Plant Law, 2015”. 111 TheMinister for Science and Technology, Yeafesh Osman, stated that the actual budget would not yetbe under discussion. “As for now, we are trying to understand the components of construction.” 112On 4 June 2015, Bangladesh's Finance Minister, AMA Muhith, recalled the target of 2 GWoperational by 2022 and 4 GW by 2030. 113“The quest for setting up a nuclear power plant in Bangladesh’s Rooppur is even older than thecountry’s independence”, a recent book review of “Nuclear Power & Rooppur” by Abdul Matinnoted. 114 It remains to be seen whether the country has moved much closer to the goal.Jordan has been encouraging the development of nuclear power for some decades and hasdiscussed possible projects with Atomic Energy Canada Limited (AECL), GDF‐Suez, AREVA, andKorea Electric Power Corporation (KEPCO). In May 2010, three consortia were shortlisted: theproposed designs were the ATMEA‐1 (from a consortium of AREVA and Mitsubishi HeavyIndustries (MHI), as projected in Turkey), EC6 (from AECL), and the AES‐93 (from Rosatom).However, on 30 May 2012, the Jordanian parliament approved a recommendation to shelve theprogram, as it was said it would “drive the country into a dark tunnel and will bring about anadverse and irreversible environmental impact”. The parliament also recommended suspendinguranium exploration until a feasibility study is done. 115 Prior to the vote, the Parliament’s EnergyCommittee had published a report accusing the Jordanian Atomic Energy Commission (JAEC) ofdeliberately “misleading” the public and officials over the program by “hiding facts” related tocosts. 116 The JAEC responded by saying it wouldn’t be able to produce a full evaluation until thestart of construction of the plant. 117Despite the parliamentary opposition, in October 2013, JAEC announced that Rosatom was thepreferred bidder. The value of the engineering, procurement and construction contract is said tobe US$10 billion for the two 1000 MW units. 118 It is suggested that Jordan will cover 50.1 percent110 NIW, “News Briefs”, 6 June 2014.111 The Daily Star, “Cabinet okays Rooppur nuclear power plant draft”, 4 May 2015, seehttp://www.thedailystar.net/country/cabinet‐okays‐rooppur‐nuke‐power‐plant‐draft‐80446, accessed7 June 2015.112 The Daily Star, “Nuke power plant cost up three times”, 17 May 2015, seehttp://www.thedailystar.net/frontpage/nuke‐power‐plant‐cost‐three‐times‐82738, accessed 7 June 2015.113 The Daily Star, “No new in energy”, 5 June 2015, see http://www.thedailystar.net/backpage/no‐newenergy‐92401,accessed 7 June 2015.114 The Daily Star, “Decoding Rooppur…”, 18 May 2015, see http://www.thedailystar.net/bookreviews/decoding‐rooppur‐83116,accessed 7 June 2015.115 Jordan Times, “Deputies vote to suspend nuclear project”, 30 May 2012, seehttp://jordantimes.com/Deputies+vote+to+suspend+nuclear+project‐48497, accessed March 2015.116 Ibidem.117 Monitor Global Outlook, “Jordan clings on to nuclear ambitions, despite delays”, 10 January 2014, seehttp://monitorglobaloutlook.com/news‐story/jordan‐clings‐on‐to‐nuclear‐ambitions‐despite‐delays/,accessed July 2014.118 It remains unclear what the US$10 billion would actually cover, as the construction of two units wouldcost rather twice that amount.Mycle Schneider, Antony Froggatt et al. World Nuclear Industry Status Report 2015 50
- Page 2: This page is intentionally left bla
- Page 9: Figure 32: Age Pyramid of the 131 N
- Page 12 and 13: new company called Uniper. And in A
- Page 14 and 15: Reactor Status and Nuclear Programs
- Page 16 and 17: in 2015. Historic analysis shows th
- Page 18 and 19: Olympic swimming pools. A groundwat
- Page 20 and 21: "For all intents and purposes, AREV
- Page 22 and 23: On 8 June 2015, the U.S. utility in
- Page 24 and 25: The world’s nuclear statistics re
- Page 26 and 27: According to the latest assessment
- Page 28 and 29: first in which there was zero nucle
- Page 30 and 31: definitive closure of the Indian re
- Page 32 and 33: Table 1: Nuclear Reactors “Under
- Page 34 and 35: and ‐4 in Ukraine are approaching
- Page 36 and 37: Figure 9: Construction Starts in th
- Page 38 and 39: ecent design and compliant with sig
- Page 40 and 41: clear that the 3/11 events had an i
- Page 42 and 43: Figure 15: The 40‐Year Lifetime P
- Page 44 and 45: Bangladesh, Belarus, Turkey, UAE, a
- Page 46 and 47: eports on the faulty components’
- Page 48 and 49: January 2015, both the Chamber of T
- Page 52 and 53: of the contract, with Rosatom cover
- Page 54 and 55: start construction in the next 2-3
- Page 56 and 57: In the late 1990s, the nuclear indu
- Page 58 and 59: AES‐2006 have received orders, wh
- Page 60 and 61: shortage of skilled labor; quality
- Page 62 and 63: use of passive features in the EPR
- Page 64 and 65: there have been a number of other i
- Page 66 and 67: standardize. Without standardizatio
- Page 68 and 69: Leningrad‐2‐1 Russia AES‐2006
- Page 70 and 71: ut noted that these “had varying
- Page 72 and 73: (IRIS) design. The design started i
- Page 74 and 75: or early 2013. 219 In 2011, it was
- Page 76 and 77: national energy bureau around two w
- Page 78 and 79: scale they would manage to lower th
- Page 80 and 81: The top of the reactor building of
- Page 82 and 83: TEPCO and the Government are planni
- Page 84 and 85: out that TEPCO’s lax management o
- Page 86 and 87: physical condition or suicide (“e
- Page 88 and 89: In March 2015, Fukushima Prefecture
- Page 90 and 91: “Rising long‐term natural gas p
- Page 92 and 93: projects came in at an average of U
- Page 94 and 95: Figure 20: Wind, Solar and Nuclear,
- Page 96 and 97: to rapidly accelerate the use of lo
- Page 98 and 99: • In Germany, renewables provided
- Page 100 and 101:
target is undoubtedly ambitious, bu
- Page 102 and 103:
Annex 1: Overview by Region and Cou
- Page 104 and 105:
U.S. that have “shown interest in
- Page 106 and 107:
The construction of Angra‐3 was s
- Page 108 and 109:
project boosted the nameplate capac
- Page 110 and 111:
Shuttering old, uneconomic reactors
- Page 112 and 113:
In the case of Vogtle, a report for
- Page 114 and 115:
limit their competitiveness to meet
- Page 116 and 117:
generation projects in oversupplied
- Page 118 and 119:
identified and solved will we allow
- Page 120 and 121:
commercial operation only on 31 Dec
- Page 122 and 123:
TEPCO that its staff had deliberate
- Page 124 and 125:
produce plutonium for use in MOX fu
- Page 126 and 127:
Power's Takahama‐3 and ‐4, with
- Page 128 and 129:
Kansai Electric, along with Kyushu
- Page 130 and 131:
permanent closure of five reactors
- Page 132 and 133:
contractor and China Nuclear Indust
- Page 134 and 135:
in May 2013, when the NSSC, followi
- Page 136 and 137:
The political consequences of the m
- Page 138 and 139:
The European Union 28 member states
- Page 140 and 141:
In the absence of any successful ne
- Page 142 and 143:
of the serious concerns by a range
- Page 144 and 145:
negative outlook, “owing to conti
- Page 146 and 147:
The average age of France’s power
- Page 148 and 149:
EDF shares lost up to 85 percent of
- Page 150 and 151:
power output is expected to rise si
- Page 152 and 153:
low 639 , and coal‐fired generati
- Page 154 and 155:
under construction. It was therefor
- Page 156 and 157:
utilize the fuel that it obtained b
- Page 158 and 159:
opinion at any of the sites propose
- Page 160 and 161:
In Bulgaria, nuclear power provided
- Page 162 and 163:
criteria defined in the tender”.
- Page 164 and 165:
signed a binding agreement that mad
- Page 166 and 167:
let the reactor operate until 2026.
- Page 168 and 169:
time of ordering, the reactors were
- Page 170 and 171:
intergovernmental agreement to comp
- Page 172 and 173:
Takahama‐1 (PWR) 826 1974 - 40 10
- Page 174 and 175:
IAEA have chosen to limit the LTS c
- Page 176 and 177:
Note: SFP: Spent Fuel Pool, RPV: Re
- Page 178 and 179:
Table 10: Definition of Credit Rati
- Page 180 and 181:
Monticello 3/71 3/05 11/06Palisades
- Page 182 and 183:
(as of 10 June 2015) 764Table 12: C
- Page 184 and 185:
2. Chinese Nuclear Power Plants Und
- Page 186 and 187:
2006-08, he carried out research at
- Page 188 and 189:
CGN or CGNPC - Chinese General Nucl
- Page 190 and 191:
INS - Indian Nuclear SocietyINSAC -
- Page 192 and 193:
NSSC - Nuclear Safety and Security
- Page 194 and 195:
UNSCEAR - United Nations Scientific
- Page 196 and 197:
Romania 2 1 300 14 18. 5% (‐) 8%
- Page 198 and 199:
Shandong Shidaowan 200 01/12/12 2/2
- Page 200 and 201:
USA 5 5 633Virgil C. Summer‐2 111
- Page 202:
25 Delayed numerous times. Latest I