Tendering System<br />

After underst<strong>and</strong>ing the legal system as described above, this section considers the system of public<br />

procurement-related institutions. Table 14 describes the tendering systems <strong>for</strong> public works<br />

implemented in different countries. The bidding <strong>and</strong> contract methods <strong>for</strong> public work contracts in<br />

Japan are different from those in other countries because each country has created them to reflect<br />

the features of its construction market, economic institutions, <strong>and</strong> practices.<br />

The characteristic tendering systems in the US is based on competitive negotiated proposals <strong>and</strong> the<br />

best value. Under the system of competitive negotiated proposals, the government presents<br />

a ”Request <strong>for</strong> Proposal (RFP)” to bidders, <strong>and</strong> the bidders submit proposals to meet the needs of<br />

the government. The government then examines <strong>and</strong> evaluates the proposals to choose a contractor<br />

from among them. In this process, the government is allowed to discuss with bidders regarding<br />

defects of their specifications, <strong>and</strong> the bidders are given the opportunity to revise their proposals<br />

be<strong>for</strong>e the selection of a successful bidder. In this negotiation process, the government will not<br />

disclose the names of other bidders, the number of these competitors, <strong>and</strong> the proposals made by<br />

other bidders, <strong>and</strong> each bidder will make ef<strong>for</strong>t to create the best proposal to win a contract, which<br />

will promote competitive pricing. In competitive negotiated proposals, the government needs to<br />

predefine factors to be evaluated to ensure the “best value” <strong>for</strong> the government. The government<br />

should always consider various factors, including price, quality, qualification of employees,<br />

business management, <strong>and</strong> past per<strong>for</strong>mance. In evaluating these factors, it is required to attribute<br />

more importance to a narrative description than to a quantitative evaluation <strong>and</strong> rating by scores,<br />

<strong>and</strong> the evaluation results should be explained by narrative descriptions.<br />

The biggest feature of Japan's traditional bidding system, however, is that it lacks competitiveness<br />

compared to other countries. For example, the “designated competitive bidding system”, which can<br />

preclude the general entering, is widely conducted <strong>for</strong> public works 22 . As <strong>for</strong> the criteria <strong>for</strong> being<br />

awarded a contract, the lowest bid price was adopted as the principal criterion 23 , which can hardly<br />

prevent collusive bidding. In addition, the Public Accounting Law does not permit any negotiations<br />

<strong>for</strong> placing orders <strong>for</strong> public works, <strong>and</strong> the national government does not negotiate with bidders.<br />

These characteristic institutions have eliminated the competition, <strong>for</strong>med a hotbed of bid rigging,<br />

<strong>and</strong> created a mechanism that produces cozy relationships, including the protection of local<br />

suppliers.<br />

22 The open <strong>and</strong> competitive bidding system is conducted <strong>for</strong> large public works that are covered by the WTO Agreement<br />

on Government Procurement.<br />

23 In fiscal 1999, however, competitive bidding in which not only the bid price but also technical advantages <strong>and</strong> quality<br />

are evaluated (called “technical proposal integrated evaluation system”) was also approved based on comprehensive<br />

agreement with the Minister of Finance. It should be noted that the bidding method of <strong>PFI</strong> applies “Integrated Evaluation<br />

Method (Open Tendering)” in principle rather than the lowest price as described above.<br />

84