The <strong>installation</strong> process is further aided if, when each base is set in place, a very rough leveling procedure is<br />
done. The ideal distance from the floor to the bottom of the two bases is 2.5” (64mm). The use of a machinist<br />
scale or small gauge blocks will expedite the process. While all leveling screws and leveling pads are in place<br />
measure from the floor to the bottom of each base until the distance is very close to the 2.5” (64mm) height.<br />
This will accomplish two things: First, that the machine is set to the proper height to receive the coolant tank<br />
and, second, that the machine will be much closer to level than without having done this procedure.<br />
The <strong>installation</strong> procedure follows the general outline below (a more detailed explanation follows). Depending<br />
on the available space and equipment it may be simpler to place the column base assembly before the table<br />
base assembly. This outline considers that it is easier to place the table base assembly first.<br />
Regardless of which assembly is placed first, adhere to the concepts of this general outline:<br />
• Remove the table base assembly from the truck and set in place<br />
• Remove the X-axis auger trough and rough level the table base<br />
• Stone and clean the table base mating flange<br />
• Remove the column base assembly from the truck<br />
• Stone and clean the column base mating flange<br />
• Move the column base to mate with the table base<br />
• Be certain that all connecting bolts are in place but not tightened<br />
• Attach the Pendant and Pendant Arm Support Assembly to the front of the table base<br />
• Run Pendant electrical wires under the table and connect them in the wire covers on the back of the table<br />
• Rough level the column base assembly<br />
• Remove the dust covers from the column assembly<br />
• Install the counterbalance cylinder and charge the system<br />
• Remove shipping blocks from the table base assembly<br />
• Connect all air/electrical/oil lines between the two assemblies<br />
• Remove shipping blocks from the column base assembly<br />
• Power up the control<br />
• Fine level the table base assembly<br />
• Fine level/square the column base assembly<br />
• Fully tighten the connecting bolts and adjust fine level/square<br />
• Fully check machine geometry<br />
• Replace the X-axis auger trough<br />
• Install the coolant supply system<br />
• Check all motors for rotation/phasing<br />
Machine levelinG and GeoMetRy check (vs)<br />
At this point the machine is completely unblocked and all axes are enabled.<br />
Column Base<br />
Mating Flange<br />
SHCS (19)<br />
Cable Access<br />
Hole<br />
Table Base<br />
Mating<br />
Flange<br />
Lockwasher<br />
(19)<br />
26 Installation 96-0284A<br />