3. Install and verify operation of the tool changer (see the section on tool changer <strong>installation</strong> and alignment<br />

for the specific toolchanger). Verify all machine functions.<br />

spindle sweep<br />

Cable<br />

Support<br />

Clamp<br />

Cable<br />

X-Axis Auger<br />

Trough<br />

Cable (To X-Axis<br />

Auger Motor)<br />

X-Axis<br />

Cable<br />

X-Axis Auger Trough<br />

NOTE: The machine must be properly leveled for the spindle sweep adjustment to be<br />

accurate; no more than .0002” twist on the Y-axis (vert <strong>mill</strong>).<br />

1. To check spindle sweep, place a .0005” indicator on a suitable holder, place on spindle nose and jog the<br />

Z-axis in the negative (-) direction enough so that you can adjust the indicator to sweep a 5" radius from the<br />

center of X- and Y-axis travel. Slowly jog Z-axis in the negative (-) direction to zero out indicator.<br />

2. Establish a reference point (indicator zero), sweep the three remaining points and record the reading.<br />

coolant tank <strong>installation</strong><br />

Spindle Sweep Area<br />

10" dia.<br />

circle<br />

1. The coolant pump(s) is packed inside the machine enclosure for shipping.<br />

2. Remove the handle from under the coolant tank lid. Remove the packing material and use the supplied<br />

hardware to attach the handle to the tank.<br />

NOTE: Do not fill the coolant tank before removing the handle from under the lid.<br />

3. Orient the pump(s) and lower into the coolant tank as shown. Place supplied cover as shown. When not<br />

using a TSC pump, install a double lid in place of the single lid (see illustration).<br />

4. Position the coolant tank under the left side of the machine.<br />

32 Installation 96-0284A<br />