Shipping<br />

Position<br />

Operating<br />

Position<br />

After the machine is installed, the High Intensity Lighting option must be reconfigured from its shipping<br />

position. To do this, perform the following steps on the right light assembly.<br />

1. Remove the BHCS securing the cover to the light arm. Remove the cover.<br />

2. Remove the two BHCS securing High Intensity Light assembly to header bar. Loosen (not remove) center<br />

pivot screw. Remove the two BHCS from threaded holes in header bar. Rotate light assembly 180°. Line up<br />

holes in light assembly with threaded holes in header bar. Insert removed BHCS and tighten all five screws.<br />

FRONT<br />

Pivot Screw<br />

(loosen only)<br />

Remove 4screws<br />

TOP VIEW OF MACHINE<br />

(Temporary shipping configuration)<br />

FRONT<br />

3. Take up any slack in the power cables. Tighten the strain-relief nuts.<br />

Secure Bracket using<br />

these 5screws<br />

TOP VIEW OF MACHINE<br />

(Setup Complete)<br />

4. Attach High Intensity Light cover to back of the light assembly and secure with screws removed in step 1.<br />

accessoRy table<br />

The Accessory Table is wrapped and shipped in the machine.<br />

Unwrap and install the table in the provided mounting brackets on the front of the machine.<br />

42 Installation 96-0284A<br />

© <strong>Haas</strong> <strong>Automation</strong> June 2010