NOTE: Before operating the coolant system, ensure the machine drain is positioned halfway<br />
over pull out chip tray.<br />
oil/coolant sepaRatoR<br />
The oil/coolant separator may be shipped installed or no installed depending on the machine configuration.<br />
If the separator is not in place, install the assembly to the nipple on the base casting. Install the aluminum<br />
tube to the fitting on the back of the separator.<br />
Once installed, check the level of the separator (use the built-in bubble level) and tighten the jam nut.<br />
auxiliaRy FilteR<br />
NOTE: Never reuse waste oil from the Oil/Coolant Separator; dispose of properly.<br />
Standard Coolant Systems<br />
Level<br />
Sensor<br />
Lid<br />
Gate<br />
Filter<br />
Double<br />
Lid<br />
Handle<br />
Standard<br />
Pump<br />
Auxiliary<br />
Filter<br />
Replacement<br />
Filter Bag<br />
Holder<br />
VF Series Machines Shown<br />
To<br />
Spindle<br />
Head<br />
Installation<br />
1. Place the Auxiliary Filter system next to the coolant tank of the machine.<br />
2. Connect the output of the Standard Coolant pump to the input of the Auxiliary Filter.<br />
3. Connect the Auxiliary Filter output hose to the coolant hose of the machine.<br />
4. The Auxiliary Filter tank must be filled with coolant before use.<br />
Standard<br />
Pump<br />
Auxiliary<br />
Filter<br />
34 Installation 96-0284A<br />
© <strong>Haas</strong> <strong>Automation</strong> June 2010