The loading consisted of many elements. On shore the export cable was equipped with a<br />

cable engine at each end of the cable, one at the storage space and one at the quay,<br />

figure 8. The onshore cable engines were operated one at a time. Behind each cable<br />

engine there was a slack on the cable that is constant at the right velocity. On the barge<br />

there were two additional pulling devices before the cable coiled onto the turntable.<br />

Figure 8. In a tent on the quay a second pulling device was placed. In the tent the cable was marked at exact<br />

lengths.<br />

Because of the necessary slack behind the cable engine the barge had to be moored<br />

approximately 15 meters from the quay, figure 9.<br />