December 2, 2006:<br />
Figure 10. The motor installed with the wheel pressing onto the cable at the capstan.<br />
With the help of the electric motor and wheel, the whole length of the cable was loaded<br />
onboard. An average speed of loading of 5-6 meters per minute was planned, but at times<br />
the speed was exceeding 10 meters per minute. When the loading was finished, a fibre<br />
test confirmed that the tension in the cable was accurate.<br />
5.1.3 Pre-laying and bad weather conditions<br />
The issues identified during loading raised questions about the ability to lay and reload the<br />
cable in the case of bad weather conditions. Carrying out a pre-laying exercise in a<br />
neighbouring archipelago solved this.<br />
Before the pre-laying exercise was carried out, a new construction was added to the<br />
“gooseneck” which included an extra vespa. The new construction was an extension of the<br />
“gooseneck” where the vespa was built-in, figure 11.<br />