6.3.3 On the foundations<br />

To ensure that enough cable was provided to each foundation, the cable was pulled 6 -<br />

8 meters above the j-tube top. The cable armour was removed for this length before the<br />

cable was secured, see figure 26 below.<br />

Figure 26. The cable armour was removed with help of an angle grinder<br />

At every foundation where the cable laying was ending there was more cable than<br />

necessary. This extra length of cable was cut off using a tiger saw, figure 27.<br />

Figure 27. A tiger saw was used to cut the excess length of cable<br />