Figure 14. The cable pull-in at the shoreline made by the excavator and a pull-in winch.<br />

When the pull-in was ready the cable was submerged into the pre-excavated trench.<br />

December 19, 2006:<br />

The floating bags that were used during the submerging of the cable were not disposed of<br />

immediately, which caused temporary debree scattered along the shoreline. Divers walked<br />

or swam the whole shoreline in the bay to collect floating bags, figure 15.<br />

Figure 15. The shoreline was filled of floating bags after the submerging.<br />

18 (30)