Figure 14. The cable pull-in at the shoreline made by the excavator and a pull-in winch.<br />
When the pull-in was ready the cable was submerged into the pre-excavated trench.<br />
December 19, 2006:<br />
The floating bags that were used during the submerging of the cable were not disposed of<br />
immediately, which caused temporary debree scattered along the shoreline. Divers walked<br />
or swam the whole shoreline in the bay to collect floating bags, figure 15.<br />
Figure 15. The shoreline was filled of floating bags after the submerging.<br />