During the cable laying, when the trench was completed, the impact on the environment<br />
was considerably lower. The clay particles normally settled very quickly, often within less<br />
than an hour.<br />
A minimum of one meter of installation depth was required, but was not met in some<br />
locations. Close to the shore, some rocks were found in the trench while the cable was<br />
being water jetted. The installation at a depth of half a meter was approved in these cases<br />
because blasting would be a much worse alternative from an environmental point of view.<br />
At trench sections where the depth was less than half a meter, the trench had to be covered<br />
by rocks.<br />
8 REFERENCES<br />
[1] Ljung, P. Method description Array cable installation for <strong>Lillgrund</strong>. February 21, 2007<br />
[2] Madsen, M. Conversation during the first inter-array cable laying. May 11, 2007<br />