December 3, 2006:<br />

Figure 11. An extension was built on the “gooseneck” where the vespa was built-in.<br />

A practice run with about 50 meters of cable was pre-laid, on a similar depth as <strong>Lillgrund</strong><br />

(10 meters). The practice run in the archipelago worked out very well. Due to the<br />

difficulties loading the cable the barge had been delayed for about two days but was now<br />

finally ready for the transit to Klagshamn.<br />

December 3-15, 2006:<br />

During this particular period there were poor weather conditions on the south coast of<br />

Sweden. The barge had to wait in Karlskrona an additional few days for better weather.<br />

When the barge finally sailed to Klagshamn, the weather conditions were too bad for cable<br />

laying and the barge had to wait in the harbour of Limhamn.<br />

5.2 Pull-in of the cable<br />

December 16, 2006:<br />

After two weeks of waiting for better weather, it was finally time to make the pull-in of the<br />

export cable. The weather forecast predicted acceptable weather conditions for the next<br />

couple of days, so the barge went out to the starting position.<br />

December 17, 2006:<br />

The weather made a turn for the worse and made it impossible to guarantee a safe pull-in.<br />

December 18, 2006:<br />

The weather conditions improved and an attempted pull-in of the cable was approved.<br />

Although the barge had moved slightly from its position due to the wind, this did not pose a<br />