04.06.2013 Views

HARBOR SYSTEM MASTER PLAN - City and Borough of Sitka

HARBOR SYSTEM MASTER PLAN - City and Borough of Sitka

HARBOR SYSTEM MASTER PLAN - City and Borough of Sitka

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

12 SEALING COVE <strong>HARBOR</strong> BOAT LAUNCH RAMP<br />

IN KIND REPLACEMENT BUDGETARY ESTIMATE<br />

Prepared By: PND Engineers, Inc., February 2012<br />

Item Item Description Units Quantity Unit Cost Amount<br />

12A MARINE FACILITIES<br />

1 Mobilization LS All Reqd 10% $65,000<br />

2 Demolition & Disposal LS All Reqd $30,000 $30,000<br />

3 Construction Surveying LS All Reqd $15,000 $15,000<br />

4 Base Course, Grading A CY 150 $50 $7,500<br />

5 Riprap, Class II CY 300 $50 $15,000<br />

6 Concrete Apron <strong>and</strong> Abutment LS All Reqd $40,000 $40,000<br />

7 Precast Concrete Ramp Planks LS All Reqd $240,000 $240,000<br />

8 Timber Boarding Float LS All Reqd $250,000 $250,000<br />

9 Steel Pipe Pile, 12.75" dia. x 0.500" thick EA 5 $7,500 $37,500<br />

10 Predrilled Pile Sockets (assume 60%) EA 3 $5,000 $15,000<br />

ESTIMATED CONSTRUCTION BID PRICE $715,000<br />

CONTINGENCY (15%) $107,250<br />

ENVIRONMENTAL PERMITTING, FINAL DESIGN, CONTRACT<br />

ADMINISTRATION, CONSTRUCTION INSPECTION & OTHER<br />

INDIRECT COSTS (20%)<br />

$143,000<br />

TOTAL RECOMMENDED PROJECT BUDGET $965,250<br />

12B U<strong>PLAN</strong>D ACCESS AND PARKING<br />

1 Mobilization LS All Reqd 10% $18,200<br />

2 Excavation <strong>and</strong> Demolition & Disposal LS All Reqd $12,000 $12,000<br />

3 Base Course, Grading D-1 CY 500 $50 $25,000<br />

4 Storm Drain System LS All Reqd $50,000 $50,000<br />

5 3" ACP Paving SY 1000 $55 $55,000<br />

6 Painting & Striping LS All Reqd $7,500 $7,500<br />

7 Construction Surveying LS All Reqd $7,500 $7,500<br />

8 Electrical/Lighting System LS All Reqd $25,000 $25,000<br />

ESTIMATED CONSTRUCTION BID PRICE $200,200<br />

CONTINGENCY (15%) $30,030<br />

ENVIRONMENTAL PERMITTING, FINAL DESIGN, CONTRACT<br />

ADMINISTRATION, CONSTRUCTION INSPECTION & OTHER<br />

INDIRECT COSTS (20%)<br />

$40,040<br />

TOTAL RECOMMENDED PROJECT BUDGET $270,270<br />

Note: Costs for expansion to two-lane facility are not included in this estimate.<br />

73<br />

<strong>Sitka</strong> Harbor System Master Plan<br />

Condition Inventory

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!