12 SEALING COVE <strong>HARBOR</strong> BOAT LAUNCH RAMP<br />
IN KIND REPLACEMENT BUDGETARY ESTIMATE<br />
Prepared By: PND Engineers, Inc., February 2012<br />
Item Item Description Units Quantity Unit Cost Amount<br />
12A MARINE FACILITIES<br />
1 Mobilization LS All Reqd 10% $65,000<br />
2 Demolition & Disposal LS All Reqd $30,000 $30,000<br />
3 Construction Surveying LS All Reqd $15,000 $15,000<br />
4 Base Course, Grading A CY 150 $50 $7,500<br />
5 Riprap, Class II CY 300 $50 $15,000<br />
6 Concrete Apron <strong>and</strong> Abutment LS All Reqd $40,000 $40,000<br />
7 Precast Concrete Ramp Planks LS All Reqd $240,000 $240,000<br />
8 Timber Boarding Float LS All Reqd $250,000 $250,000<br />
9 Steel Pipe Pile, 12.75" dia. x 0.500" thick EA 5 $7,500 $37,500<br />
10 Predrilled Pile Sockets (assume 60%) EA 3 $5,000 $15,000<br />
ESTIMATED CONSTRUCTION BID PRICE $715,000<br />
CONTINGENCY (15%) $107,250<br />
ENVIRONMENTAL PERMITTING, FINAL DESIGN, CONTRACT<br />
ADMINISTRATION, CONSTRUCTION INSPECTION & OTHER<br />
INDIRECT COSTS (20%)<br />
$143,000<br />
TOTAL RECOMMENDED PROJECT BUDGET $965,250<br />
12B U<strong>PLAN</strong>D ACCESS AND PARKING<br />
1 Mobilization LS All Reqd 10% $18,200<br />
2 Excavation <strong>and</strong> Demolition & Disposal LS All Reqd $12,000 $12,000<br />
3 Base Course, Grading D-1 CY 500 $50 $25,000<br />
4 Storm Drain System LS All Reqd $50,000 $50,000<br />
5 3" ACP Paving SY 1000 $55 $55,000<br />
6 Painting & Striping LS All Reqd $7,500 $7,500<br />
7 Construction Surveying LS All Reqd $7,500 $7,500<br />
8 Electrical/Lighting System LS All Reqd $25,000 $25,000<br />
ESTIMATED CONSTRUCTION BID PRICE $200,200<br />
CONTINGENCY (15%) $30,030<br />
ENVIRONMENTAL PERMITTING, FINAL DESIGN, CONTRACT<br />
ADMINISTRATION, CONSTRUCTION INSPECTION & OTHER<br />
INDIRECT COSTS (20%)<br />
$40,040<br />
TOTAL RECOMMENDED PROJECT BUDGET $270,270<br />
Note: Costs for expansion to two-lane facility are not included in this estimate.<br />