PROJECT: SR <strong>60</strong> TRAFFIC CALMING<br />
Wednesday, December 12, 2012<br />
OPINION OF PROBABLE CONSTRUCTION COSTS - CONCEPTUAL STRIPING<br />
"The Engineer has no control over the cost <strong>of</strong> labor, materials, equipment or services furnished by others, or over the Contractor's methods <strong>of</strong><br />
determining prices, or over competitive bidding or market conditions. Opinions <strong>of</strong> probable costs provided herein are based on the information known to<br />
the Engineer at this time and represent only the Engineer's judgment as a design pr<strong>of</strong>essional familiar with the construction industry. The Engineer<br />
cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinion <strong>of</strong> probable costs."<br />
PAY DESCRIPTION UNIT PROJECT UNIT PROJECT<br />
ITEM NO. QUANTITY PRICE COST<br />
ROADWAY<br />
101-1 MOBILIZATION LS 1 $ 50,000 $<br />
50,000<br />
102-1 MAINTENANCE OF TRAFFIC LS 1 $ 50,000 $<br />
50,000<br />
104-10-3 EROSION CONTROL LS 1 $ 15,000.00 $<br />
15,000<br />
PROFESSIONAL ENGINEERING LS 1 $ 50,000 $<br />
50,000<br />
CONSTRUCTION ENGINEERING AND INSPECTION LS 1 $ 50,000 $<br />
50,000<br />
108-1 AS-BUILTS LS 1 $ 10,000 $<br />
10,000<br />
327-70-6 MILLING EXISTING ASPHALT PAVEMENT 1 1/2" AVG DEPTH SY 29,255 $ 2.25 $<br />
65,824<br />
334-1-13 SUPERPAVE ASPHALTIC CONCRETE (TRAFFIC C) 9.5 TN 2,415 $ 110.00 $<br />
265,650<br />
SIGNING AND MARKING<br />
700-20-11 SINGLE POST SIGN (F&I) (