119 <br />

Convectron gauge in Manifold has problem: Try to readjust or replace.<br />

Markus + Christian; starts with 17 and 123. Oct. 15. => Manifold<br />

convectron gauge shows right pressure.<br />

120 Repair Phillips CFD 715: Center channel jumps in time (seen on<br />

computer, it is not a cable delay problem). Give to Eric Henson. Totti<br />

did it<br />

January<br />

2009<br />

8/15/2008<br />

121 Repair Ortec 441 R<strong>at</strong>emeter. Give to Eric Henson. Totti did it 8/15/2008<br />

122 Powersupply of Helmholtz coils: Display is broken; maybe more. Give<br />

to EM shop. Totti did it. Back from repair. Should work.<br />

123 Open the jet which got clogged during summer beamtime: Clean the<br />

nozzle. Get new Swagelok filter. Remove mesh in front of nozzle !?<br />

Totti prepared dismount of turbo pump. Markus + Christian. Markus<br />

cleaned nozzle and put stuff back together. Jettest and vacuum test<br />

(also of the phosphor feedthrough) is still needed. First test gave<br />

factor too small rise in jetdump. Reopened and reduced the distance<br />

to skimmer from 11 to 5 mm. Now jet is working fine (no new filter was<br />

implemented though).<br />

8/15/2008<br />

1/21/2009<br />

124 Check all 5 NIM bins (each slot) <strong>for</strong> voltages. Totti did it 8/16/2008<br />

125 Pin <strong>at</strong> 120mm quad anode fell off. Solder…. Totti did it 8/16/2008<br />

126 Re-center the Chamber on the frame. Adjust the little frame <strong>for</strong> the<br />

differential pumping stage. Totti did it<br />

127 SAFTEY: Earthquake brackets <strong>for</strong> Chambers in 102 and 104 are not<br />

safe. Redesign needed. Totti did it – prototype will be made by Rene.<br />

Prototype is now revised. Rene is making 12 stereotypes. Done and<br />

installed<br />

128 Harddrives in d<strong>at</strong>a acquisition and d<strong>at</strong>a analysis computer have to be<br />

replaced. Perhaps order four 500 GB HDs (check if BIOS would be<br />

happy with th<strong>at</strong>). Think of the possible options. M<strong>at</strong>thias ordered HDs<br />

and they arrived. However, there are not mounted yet. Markus will<br />

replace some: see 148.<br />

129 Monitor of d<strong>at</strong>a analysis computer has a problem. Might be still under<br />

warranty. Totti is on it. Sent it out <strong>for</strong> repair. Came back and was also<br />

broken. Send out again. Came back and works.<br />

130 SAFETY: Multiple outlets near w<strong>at</strong>er lines (within 6 feet) need plastic<br />

box: Totti did it<br />

8/16/2008<br />

9/9/2008<br />

12/01/2008<br />

9/11/2008<br />

8/22/2008<br />

11