196 11/17/09 Fast Lothar NIM CFD’s need test <strong>for</strong> time jitter or walk<br />

problem according to Markus’ analysis. Markus runs test and is in<br />

contact with Lothar – might exchange or repair them over Christmas.<br />

Lothar things it was a bad walk and threshold adjustment. No test<br />

were done.<br />

197 <br />

12/15/09 Look <strong>for</strong> CO and order, also talk to Donna. Markus ordered 2<br />

midsize bottles. Bottle arrived and is outside building 7 (locked).<br />

Bottles labeled<br />

and put in ALS gas storage.<br />

198 12/15/09 Resize Helmholtz cage after moving? May be needs to be a<br />

little bigger. Markus: New Cable/Clamps and Rods are ordered and<br />

arrived. Cage posts need to be further apart + old and new rods need<br />

to be cut + install new cable. 1/7/10 Totti made new stand-offs in<br />

machine shop and mounted them. Exchanged Al rods <strong>at</strong> the vertical<br />

side. New horizontal rods need to be measured, cut and mounted:<br />

Done 1/8/10. Florian and Totti adjusted height (1/20/10). Florian and<br />

Irina installed computer cable. Resistance checked. Should work.<br />

Some cables still need to be fastened to the frame.<br />

199 <br />

12/1/09 CO spectrometer simul<strong>at</strong>ion: Design is almost finished<br />

(12/20/09). Drift tube needs to be cut + tapped holes <strong>for</strong> feet installed.<br />

CF 150-250 Adapter is needed. 8020 support <strong>for</strong> CF250<br />

spool needs<br />

to be built. Check CF250 spool (is out of the dumpster). Markus brings<br />

hexanode and mesh from Frankfurt. Totti borrowed 13 ¼ to 8 in flange<br />

(Frank Zucca) and 13 ¼ to 2 ¾ flange (Eli Rothenburg); a second 13<br />

¼ to 8 in flange would be better – got it from Bruce Rude (1/14/10).<br />

Florian and Markus build spectrometer and fitted it into chamber<br />

(3/10/10)<br />

163 12/1/09 Jet cooling still needs to be put together and tested. Gas inlet<br />

is missing. Glands have to be ordered and welded to new stainless<br />

steel tube – Glands arrived 1/710. Florian brought it to 77 (1/22/10).<br />

Parts came back and were installed. Leak found on nozzle to copper<br />

block connection (insert was tightened). Works but no big<br />

improvement <strong>for</strong> cold jet (-125C <strong>at</strong> Nozzle, -153C <strong>at</strong> Coldtrap Copper<br />

rod, ideal would be -196C).<br />

200 1/19/10 D<strong>at</strong>a acquisition computer crashed with blue screen<br />

and was<br />

unstable after reboot. Totti imaged oper<strong>at</strong>ing system to a new<br />

harddrive with IT service and exchanged SATA cable.<br />

201 1/26/10 Connectors <strong>for</strong> 12pin feedthrough (anode) and perhaps <strong>for</strong><br />

SHV feedthroughs are needed. Florian found pins <strong>at</strong> http://www.multicontact-usa.com<br />

– part-number 41.6000, type B1-TH (1/26/10).<br />

Orderd and arrived. Florian made new cables<br />

20/12/2009<br />

2/11/2010<br />

3/12/2010<br />

3/10/2010<br />

2/17/10<br />

1/20/10<br />

2/5/2010<br />

23