Trip circuit<br />
Indicating lamps<br />
CTs wiring<br />
MCBs input power<br />
Master Control Facility – Hassan<br />
: ACBs / MCCBs shunt trip power supply shall be taken independently<br />
through MCBs from auxiliary busbars.<br />
: Wiring for presence of input power, ACBs / MCCBs ON / OFF and fault trip<br />
status indication.<br />
: Isolators for digital TVM & shorting links for analog meters shall be used.<br />
: Multiple MCB’s input power supply should be tapped through 125A SDFU<br />
for short circuit protection.<br />
Name plates / stickers<br />
Name plate : Nameplates for Transformers & Generators incomers and each outgoing<br />
feeder outlets shall be provided.<br />
: Each nameplate shall contain feeder no, switchgear rating and<br />
nomenclature.<br />
: Nameplates size, design, and color combination and nomenclature for<br />
each output feeder will be furnished during approval of drawing.<br />
: The approved SLD of the panel shall be screen-printed / computerized<br />
print over an A3 size 2 mm thick aluminum sheet or foam board. It shall be<br />
fixed at top-center of the panel.<br />
Laminated stickers : Laminated stickers of suitable size with good quality adhesive shall be<br />
fixed at each terminal blocks, meters, relays on the inner side for clear<br />
Panel specification<br />
plate<br />
Grounding / Earthing<br />
Type<br />
Panel earth bus<br />
Switchgear<br />
Panel doors<br />
Meters / relays<br />
Inspection / Testing<br />
First stage<br />
inspection<br />
Final inspection &<br />
testing<br />
identification.<br />
: The panel shall have the specification plate as per the IS reference<br />
standard 2675<br />
-Rated voltage AC or DC Hz<br />
-Total number of outgoing ways / feeders<br />
-Rated current of each outgoing feeders<br />
-Number of poles<br />
-Manufacturer name / Trade mark / Address<br />
-Customer PO reference and date<br />
-Year of manufacturing<br />
: Two-point ground in accordance with the recommendations of IEEE<br />
Standard and the requirements of the NEC.<br />
: High-purity electrolyte copper E-Cu 57 busbar of size 50x6 mm should be<br />
run all along the width of the panel at front or rear bottom surface.<br />
: All ACBs and switchgears body shall be earthed by 25x3 mm copper strip.<br />
: Doors shall be earthed, if electrical equipment (meters / relays / lamps)<br />
mounted by a yellow green 2.5 Sq. mm wire lugged at both ends.<br />
: All meters / relays shall be earthed to the profile by a yellow green 2.5 Sq.<br />
mm wire lugged at both ends.<br />
: Mechanical -structural fabrication after approval of GA drawing.<br />
: Verification of components as per PO bill of material.<br />
: Minor modifications in mechanical / electrical changes pointed out by MCF<br />
inspecting officer shall be carried out, if necessary, without additional cost.<br />
: After integration of switchgears and wiring.<br />
: Inspection and testing as per checklist.<br />
: Calibrated testing & measuring instruments are to be used for routine test.<br />
: Any deviations from the specifications or in testing shall be attended &<br />
offered for re-inspection.<br />
Semi Modular substation LT panel –Specification 6