23.03.2014 Views

FEIS Summary - Knik Arm Bridge and Toll Authority

FEIS Summary - Knik Arm Bridge and Toll Authority

FEIS Summary - Knik Arm Bridge and Toll Authority

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Knik</strong> <strong>Arm</strong> Crossing Final EIS<br />

<strong>Summary</strong><br />

FHWA identified the Northern Access<br />

Alternative as the Preferred Alternative<br />

in the Draft EIS for the alternative’s<br />

consistency with Mat-Su Borough <strong>and</strong><br />

Port MacKenzie planning objectives<br />

(wetl<strong>and</strong> impacts, ROW impacts, <strong>and</strong><br />

construction costs are similar under<br />

both the Point MacKenzie Road<br />

Alternative <strong>and</strong> Northern Access<br />

Alternative). The Northern Access<br />

Alternative will remove through-traffic<br />

from Port MacKenzie operations, will be<br />

more conducive to Port MacKenzie<br />

development, <strong>and</strong> is favored by Mat-Su<br />

Borough <strong>and</strong> Port MacKenzie officials.<br />

Identification of Recommended<br />

Alternative<br />

No adverse comments were received<br />

during the Draft EIS comment <strong>and</strong><br />

review period regarding the<br />

identification of the Northern Access<br />

Alternative as the Preferred Alternative.<br />

The Northern Access Alternative has<br />

been identified as the Recommended<br />

Alternative for the reasons noted in the<br />

“Comparison of Impacts” section, above.<br />

Crossing<br />

Comparison of Impacts<br />

Two bridge crossing lengths were<br />

evaluated for the Southern Alignment<br />

Crossing of <strong>Knik</strong> <strong>Arm</strong>: a 14,000-foot, 3<br />

pier-supported bridge spanning the<br />

entire width of the arm, <strong>and</strong> an<br />

8,200‐foot, pier-supported bridge with<br />

armored, 4 gravel-fill roadway sections<br />

3<br />

The 14,000-foot bridge length was found to not be<br />

financially feasible <strong>and</strong> did not meet stated<br />

purpose <strong>and</strong> need criteria. This alternative was,<br />

however, carried forward solely for comparative<br />

evaluation based on requests from environmental<br />

resource <strong>and</strong> permitting agencies.<br />

4<br />

<strong>Arm</strong>or rock (3–5 feet in diameter) will be placed on<br />

the slopes of the gravel-fill roadway sections to<br />

prevent undercutting <strong>and</strong> erosion resulting from<br />

tidal currents, storm surges, wave run-up, <strong>and</strong> ice<br />

floes.<br />

completing the Crossing. 5 Either bridge<br />

length (see Exhibit S-16) could cross the<br />

intertidal zone perpendicular to the<br />

shoreline <strong>and</strong> connect to either Mat-Su<br />

side alternative.<br />

In the EIS, the Study Team considers the<br />

project’s impact to hydrologic <strong>and</strong><br />

sedimentation processes of <strong>Knik</strong> <strong>Arm</strong>.<br />

Through alteration of natural tide-driven<br />

flows in their immediate vicinity, both<br />

bridge crossings studied are capable of<br />

disturbing hydrologic <strong>and</strong> sedimentation<br />

processes. Neither bridge alternative,<br />

however, is expected to affect tidal flows<br />

or naturally occurring sedimentation in<br />

the vicinity of the POA.<br />

As the table on Exhibit S-16 shows,<br />

construction costs, construction time<br />

<strong>and</strong> methods, the use of <strong>and</strong> impact<br />

from more fill versus the driving of more<br />

piers, <strong>and</strong> impacts to essential fish<br />

habitat <strong>and</strong> to beluga whales, are key<br />

impact categories evaluated in the EIS.<br />

While the 8,200-foot <strong>Bridge</strong> Alternative<br />

will have a lower construction cost <strong>and</strong><br />

will be easier to construct, it will also be<br />

associated with more marine fill placed<br />

in essential fish habitat (including<br />

subtidal waters, estuarine shores, <strong>and</strong><br />

mudflats). More fill, however, means<br />

fewer piers to be driven. The 8,200-foot<br />

<strong>Bridge</strong> Alternative will require only<br />

about half the number of piers as would<br />

the 14,000-foot <strong>Bridge</strong> Alternative. Fewer<br />

piers also means a shorter duration of<br />

pile-driving noise, a key consideration<br />

5<br />

An intermediate single-embankment option was<br />

also considered, consisting of a 1,400-foot, gravelfill<br />

portion of the bridge crossing on the west side of<br />

<strong>Knik</strong> <strong>Arm</strong> with a 12,500-foot pier-supported bridge<br />

linking to the eastern shoreline. This option was not<br />

carried forward for further evaluation because of<br />

high operation <strong>and</strong> maintenance costs <strong>and</strong> because<br />

its estimated cost-to-impact ratio suggests that it<br />

would likely achieve only a marginal cost savings as<br />

compared with the 14,000-foot bridge alternative<br />

<strong>and</strong> would do so without reducing environmental<br />

impacts below an intermediate level. For more<br />

information please refer to KABATA’s Crossing<br />

Options Technical Report (2005d in the Draft EIS).<br />

S-11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!