TESTING:<br />

All testing instruments, velocity meter, digital thermometer, psychomotor, measuring steel tapes,<br />

tools, scaffolding <strong>and</strong> ladders etc. that may be required <strong>for</strong> taking measurements shall be arranged by<br />

air-conditioning contractor at his own cost.<br />

All types of routine <strong>and</strong> other tests shall be carried out at the works of the Contractor or the<br />

manufacturers of the components. The Client shall be free to witness any or all tests, if they so<br />

desired. The Contractor has to in<strong>for</strong>m to the Client be<strong>for</strong>e dispatch of any material / equipment.<br />

On the completion of the installation the Contractor shall arrange to carry out various initial tests as<br />

detailed below, in the presence of Owner / Consultant / Architect <strong>and</strong> to the entire satisfaction of the<br />

Owner / Consultant / Architect. Any defect or short-coming found during the tests shall be speedily<br />

rectified or made good by the Contractor at his own expenses.<br />

The initial tests shall include, but, not be limited to the following :<br />

a) To operate <strong>and</strong> check proper functioning of all electrically operated components viz. Compressor<br />

motor, pumps, fan of air h<strong>and</strong>ling units etc. as well as other electrical motors.<br />

b) To test <strong>and</strong> check the proper functioning of electrical gears, safety <strong>and</strong> other controls to ensure<br />

their proper functioning.<br />

c) To check the air distribution system <strong>and</strong> to provide designed air flow in all areas by adjusting the<br />

grills, diffusers <strong>and</strong> dampers <strong>for</strong> air-conditioning.<br />

d) To check <strong>and</strong> balance / adjust the water in the water circuit <strong>for</strong> smooth <strong>and</strong> noiseless flow.<br />

e) To check the systems against leaks in different circuits, alignment of motor, ‘V’ belt adjustments,<br />

control setting <strong>and</strong> all such other tests which are essential <strong>for</strong> smooth functioning of the plant.<br />

f) Contractor shall have to submit the capacity test of all equipment at site.<br />

g) On the satisfactory completion of all ‘Initial’ tests <strong>and</strong> one major seasonal test i.e. either summer<br />

or monsoon the plant shall be considered ‘Virtually Complete’ <strong>for</strong> the purpose of taking over<br />

by the Client.<br />

h) In addition to the ‘Initial’ test the Contractor shall also give summer <strong>and</strong> monsoon tests of the<br />

plant, each of (3) three days duration, <strong>and</strong> each one during the full specified outside conditions<br />

(when the ambient conditions are close to the specified ambient conditions). The first running<br />

test may be taken on the completion of the initial test, provided the ambient temperature <strong>and</strong><br />

humidity are near their peak. Inside condition as per the contract, per<strong>for</strong>mance of each<br />

equipment, Airflow etc. shall be as per the requirement of the contract during these tests.<br />

It is clarified that guarantee period shall start after successful completion of one major<br />

seasonal test whichever season falls earlier & inside design conditions in areas to be airconditioned<br />

temperature in the working area if any.<br />

OPERATION OF PLANT:<br />

The tenderer shall arrange to operate the plant <strong>for</strong> a period of Fifteen Days from the date of<br />

commissioning of plant <strong>and</strong> successful completion of initial test free of cost.<br />

TRAINING OF PERSONAL:<br />

The contractor shall impart training to the minimum three technical staffs appointed by the Client free<br />

of cost during erection <strong>and</strong> commissioning of the plant.