REFRIGERANT CIRCUIT:<br />
A multiple orifice control system consisting of an expansion valve <strong>and</strong> a fixed orifice, maintains<br />
refrigerant flow.<br />
MAIN CONTROL PANEL:<br />
Factory mounted main control panel is to provided with all starters, phase indicating lights, voltmeter<br />
pressure cutouts, safety switches, pre wired <strong>and</strong> factory tested etc. should be weather protected with<br />
IP- 55 protection.<br />
SELECTION OF WATER CHILLING UNIT:<br />
The Water chilling unit should be selected <strong>for</strong> the duty as specified in schedule of equipment.<br />
INSTALLATION:<br />
The chilling machine shall be installed over a cement concrete plat<strong>for</strong>m on flooring <strong>and</strong> shall be<br />
adequately isolated as per manufacturers recommendations against transmission of vibration to the<br />
building structure. For open type units, special attention shall be paid to the alignment of the drive <strong>and</strong><br />
driven shaft, final alignment shall be checked at the site<br />
in the presence of the contractor sing dial indicator.<br />
PAINTING:<br />
The Indigenous Air-cooled water Chilling machine shall be finished with durable enamel paint. The<br />
shop coats of paint that have become marred during shipment or erection, shall be cleared of win<br />
mineral spirit, wire bushed <strong>and</strong> spot primed over the effected areas, than be coated with enamel<br />
paint.<br />
PERFORMANCE RATING:<br />
The unit shall be selected <strong>for</strong> the lowest operating noise level. Capacity ratings, <strong>and</strong> power<br />
consumption with operating points clearly indicated, shall be submitted <strong>and</strong> verified at the time of<br />
testing <strong>and</strong> commissioning of the installation. The architects / consultant / clients representatives shall<br />
witness the capacity tests if need be at manufacturers works <strong>and</strong> all costs towards to <strong>and</strong> <strong>for</strong> air fare,<br />
lodging <strong>and</strong> boarding expenses shall be borne by the client.<br />
Power consumption shall be computed from measurements of incoming voltage <strong>and</strong> input current <strong>and</strong><br />
energy measure meters.<br />
TESTING:<br />
a) Unit capacity in tons refrigeration, shall be computed from the temperature reading <strong>and</strong> water flow<br />
measurements. Flow measurements shall be through flow meters. Computed results shall tally<br />
with the specified capacities as furnished with tender.<br />
b) All instruments, services needed <strong>for</strong> the test required <strong>for</strong> the computation of capacities <strong>and</strong> power<br />
consumption shall be provided by the contractors themselves. All instruments shall be calibrated<br />
<strong>and</strong> contracts shall produce calibration certificate in support.<br />
c) <strong>Tender</strong>er shall furnish detailed certificates of tests carried out on test bed in the factory.<br />
d) The total frame of air-cooled chillers should be well protected by epoxy or equivalent coating to<br />
take care of coastal installation <strong>and</strong> high sulphur contents in atmosphere to avoid corrosion.