• The cost estimate appears to be credible.<br />
• The installation schedule and manpower is well developed and credible.<br />
• The task manager illustrated high-quality ownership of the schedule.<br />
• The use of a consultant to assist in the evaluation of scintillator handling was an<br />
effective decision made by the team.<br />
The Committee suggested that the team: 1) evaluate the need for edge stiffeners;<br />
2) consider leasing a roll coating machine for prototype effort; 3) develop detailed procedures for<br />
filling the modules to assure proper process and sequence (there should be no confusion<br />
regarding filling order); and 4) complete the life safety evaluation, to include Near Detector<br />
containment.<br />
2.2.3 Recommendations<br />
1. Recommend CD-1 approval for the PVC Extrusion.<br />
2. Recommend CD-1 approval for the PVC Modules.<br />
3. Revisit the time and motion studies for module assembly using experience gained<br />
with 16-cell extrusions.<br />
4. Perform an ergonomic assessment for module assembly; in particular, the manual<br />
trolley crane movement.<br />
5. Develop a plan for use and maintenance of the vacuum lifters.<br />
6. Design the fiber retainer to maintain fiber bend radius for filling and during<br />
transportation.<br />
7. Recommend CD-1 approval.<br />
8. Develop designs for strain relief of utilities on modules.<br />
9. Develop designs for access to install utilities on the top and sides of modules blocks.<br />
10. Develop a plan for use and maintenance of the vacuum lifters.<br />
12