5. SCHEDULE and FUNDING<br />

5.1 Findings<br />

The integrated resource-loaded cost/schedule estimate for the NOνA project consists of<br />

(approximately) 3,500 schedule activities using the scheduling tool Open Plan. The project team<br />

presented a schedule range between 45-58 months for the NOνA project with a 25kT detector.<br />

The best estimate was 50 months. The project team has also identified a scope range between<br />

25kT and 34kT for a fixed TPC of $247 million (AY). Proposed DOE CD-4, Approve State of<br />

Construction, milestones were presented for each Level 2 subsystem.<br />

Sources of forward-funding outside of DOE/SC are being sought, namely from the<br />

University of Minnesota; however, to date no source can be considered firm. The NOνA<br />

management team is also actively seeking other additional funding sources outside of DOE.<br />

5.2 Comments<br />

The Committee found the 50-month schedule for a 25kT detector to be reasonable at this<br />

stage of the project. The schedule will dilate with changes to the mass scope. CD-4 dates and<br />

definitions for the project have been proposed at WBS Levels 1 and 2. The proposed DOE<br />

cooperative agreement for the building site and construction appears to be on the project critical<br />

path. Exact site and acquisition strategy will be needed at CD-2. Environmental and seasonal<br />

construction risks should be well defined prior to CD-2.<br />

Major material procurements are a key schedule risk. The project team is to be<br />

commended for confirming quotes and delivery dates/quantities to produce a credible schedule.<br />

All large procurements appear to be well advanced and delivery schedules tie in well with<br />

integration tasks.<br />

The Committee was not provided with FTE estimates or manpower profiles. Clear,<br />

supportable estimates on manpower will be needed at CD-2, which should include base program<br />

supported physicists. The project team should communicate their resource needs with the<br />

laboratory and collaboration management.<br />

Integration tasks are well developed and under capable management for CD-1. The<br />

schedule needs revisiting once the acquisition strategy is finalized. Schedule risks related to<br />