NuMi Off-Axis Neutrino Appearance - NOVA Document Database ...
NuMi Off-Axis Neutrino Appearance - NOVA Document Database ...
NuMi Off-Axis Neutrino Appearance - NOVA Document Database ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Table 4-2.<br />
NOνA Project Cost Breakdown (AY$ in Millions)<br />
WBS ITEMS Total Project<br />
Cost<br />
2.1 Far Detector Site and Building $39.7<br />
2.2 Liquid Scintillator $41.7<br />
2.3 WLS Fiber $26.2<br />
2.4 PVC Extrusions $47.8<br />
2.5 PVC Modules $15.4<br />
2.5 Electronics $21.8<br />
2.7 Data Acquisition $2.9<br />
2.8 Near Detector Assembly $1.7<br />
2.9 Far Detector Assembly $23.9<br />
2.10 Project Management $3.6<br />
Construction Subtotal $224.7<br />
PED $10.3<br />
Total TEC $235.0<br />
R&D $11.9<br />
Total Project Cost $246.9<br />
The project is currently seeking DOE approval for CD-1.<br />
The estimate includes appropriate labor rates, fringes, etc., for all institutions including<br />
Fermilab with respective overhead rates applied. Material costs include various burdening rates<br />
depending on the nature and size of the procurements. Open Plan is the software tool used to<br />
develop the project cost estimate.<br />
The project developed a bottoms-up contingency based on maturity of design using a<br />
consistent methodology for Materials and Services (M&S) and labor. The result was a<br />
contingency of (approximately) 35 percent with respect to the base cost estimate. The NOνA<br />
project has few systems but many repeatable components. In many cases, the project is dealing<br />
with known vendors and has obtained solid quotes. There are few parts that use new or<br />
unproven technologies. The conventional facilities (CF) WBS element has the lowest overall<br />
contingency at 23 percent next to project management at four percent. Less rigor was applied in<br />
developing the CF contingency estimate as compared to the methodology applied to other WBS<br />
elements. A detailed breakdown of contingency by WBS can be found in Appendix D.<br />
22